Planning the installation 

Prior to the installation, it is recommended that you 

consider future charging needs, so that you can easily 

expand accordingly in the future.

If several Charging Robots are connected to the same 

circuit, the total current is dynamically distributed 

between them. The connected Charging Robots 

communicate wirelessly between each other, ensuring 

the circuit is not overloaded. The maximum charging 

current is set during configuration.

 

For an optimal result

 

— We always recommend a 3 phase installation if 

possible, to make it future-proof.

 

— If possible, use the largest approved cable cross-

section (see 

Technical specifications

).

 

Special notes

 

— Several backplates can be connected in parallel, as 

each Charging Robot has its own protective device.

 

— If the charging infrastructure includes more than one 

Charging Robot, the backplate that is configured 

first becomes the master of its circuit.

 

— If more than 2 units are installed, the master unit 

should be located in the middle of the installation (if 

possible) for an optimal Easee Link communication.

 

Site Key: 

During installation, a Site Key must 

be used to assign the Charging Robots to the 

correct location in the Easee Cloud. A Site Key will 

automatically be generated when creating a new 

charging site using the Easee Installer App or it can 

be obtained by creating a new charging site at 

easee.cloud

.

 

Your house, power grid and EV

The Charging Robot automatically adapts to the power 

grid, the electric car and the capacity of the electrical 

installation. In the table you can see what charging 

effect you can expect from your installation and 

situation. The table is only meant as a guide.

CAUTION 

The type of installation as well as cable cross-

sections must be determined by a qualified 

electrician in accordance with valid local, regional 

and national regulations for electrical systems.

Load

Charging power

Ampere (A)

1 phase (kW)

3 phase (kW)

1

6

1.4

4.1

8

1.8

5.5

10

2.3

6.9

13

3.0

9

16

3.7

11

20

4.6

13.8

25

5.8

17.3

32

7.4

22

1

 Example for 400 V TN, deviating values for other grid 

types.

Содержание Ready

Страница 1: ...Easee Ready EN Installer guide...

Страница 2: ...UTIONS A Warning indicates a condition hazard or unsafe practice that can result in serious personal injury or death A Caution indicates a condition hazard or unsafe practice that can result in minor...

Страница 3: ...nt cover screws T25 x 5 Wall screws T25 x 4 Sealing plug x 2 Blind plug x 3 Strain relief x 2 Blind cover tool x 1 Blind cover Protects the electrical connections from external influences Backplate Fo...

Страница 4: ...A 3 phase Voltage 3x 230 400V AC 10 Mains frequency 50 Hz Protection Degree of protection IP44 Impact resistance IK10 Installation Installation network TN IT or TT detected automatically Installation...

Страница 5: ...are installed the master unit should be located in the middle of the installation if possible for an optimal Easee Link communication Site Key During installation a Site Key must be used to assign th...

Страница 6: ...ff and in accordance with local regulations Use extreme caution and follow instructions carefully Screw the locking screw at the bottom of the Easee Ready Insert the two ends of the blind cover tool i...

Страница 7: ...the Easee Mount NOTE If you are going to install multiple backplates now would be a good time to mount them as well 1 Backplate Mounting 2 Backplate Preparing 3 1 2 3 3 3 Suggested installation height...

Страница 8: ...connected with the same phase sequence External junction boxes or flat cables can be used if it is more convenient It s recommended to follow the existing colour codes used in the installation Dependi...

Страница 9: ...already has one or more Charging Robots installed or if it has been created by an operator Easee Charge select Update existing site and search for the site address On Site overview select the circuit...

Страница 10: ...e blind cover until you hear a click Screw in the blind cover screw at the bottom of the charger to secure the blind cover NOTE The locking screw is necessary to secure the cover and protect the backp...

Страница 11: ...support Download the latest manuals find answers to frequently asked questions and useful documents and videos for your product at easee support Maintenance Practical details Warranty The device is f...

Страница 12: ...n any other form by any means or in any form for your own or any third party s use unless otherwise agreed with Easee or its subsidiaries in writing Any permitted use shall always be done in accordanc...

Отзывы: