background image

OPERATING  INSTRUCTIONS:

Before filling hopper, become familiar with the operation of this spreader.  (Practice the following steps)

 

Turn the motor switch to the ON POSITION, so that the impeller is turning before going on to the next step.

 

While driving forward pull and hold the Rope to the stop, this opens the shut-off plate on the spreader.

 

To stop the flow of material, release the rope and allow the spring to return the Shut-off to its closed 

position, then turn the motor off when finished.  

TIP: Attach a sailboat rope cleat close to your operating 

position to secure the rope so you don’t need to hold it while 

spreading.

 

When finished empty any remaining material from hopper.

 

Thoroughly wash spreader and allow to dry before storing.  A light 

coating of oil will help prevent corrosion of all metal surfaces.

CALIBRATION INSTRUCTIONS:

Select the setting on the gauge, loosen wing nut and slide to setting and secure 

 

Pull Rope to ensure the stop is secure

 

Calibration is now complete

USE THE FOLLOWING PROCEDURE TO CALCULATE THE SETTING: 

 

Determine how much material is to be applied per 1,000 sq/ft.

 

Measure off a distance of 50 feet, preferably on a paved surface such as a parking lot.

 

Weigh out enough of the material to be applied to fill the hopper at least half full. Record the weight for 

future use.

 

With the unit mounted on the vehicle and the hopper at least half full of the material to be spread, position 

the vehicle far enough before the beginning of the 50 foot test area so that the vehicle will achieve the 

desired speed before you reach the starting line.

 

Set the rate setting stop at a position that you feel would be an appropriate setting.

 

Start the vehicle in motion and as you cross the starting line (of the 50 feet) move the rate lever to the open 

position against the stop. Take care to be aware of what is going on around you maintaining control of the 

vehicle.

 

Continue from the starting line with the unit spreading the material. As you cross the finish line move the 

rate lever to the closed position.

 

Stop the vehicle and note the width of the spread path that was just completed.

 

Return to the start point and empty the remaining material from the hopper into your weighing container 

and re-weigh.

RATE SETTING WORKSHEET

Desired Application Rate (lbs/1,000 sq ft) _____________

To determine the desired application rate divide the area (sq ft) the bag should cover by the weight of the bag, 

then multiply by 1,000. (Example: 5,000 sq ft / 25 lbs = .005 x 1,000 = 5)

_________   Weight of Material Placed in Hopper

- ________   Weight of Material Left in Hopper

= ________  Weight of Material Used

         50       

Length of Test Area (50 from previous page)

x ______      Width of Spread Area

= _______  

Total Spread Area

Divide the Weight of Material Used by the Total Spread Area = _________lbs\sq ft

Multiply the lbs\sq ft times 1,000 = ________lbs\1,000 sq ft

Compare the results of your test to the desired application rate.

Adjust the rate setting stop accordingly and run through the test again.  

Repeat this process until you have achieved the desired application rate.

Pull Rope

Cleat

Spreader

Operator

Отзывы: