Section 3.0 Inspection Requirements and Overhaul Schedule
3.1
Inspection Requirements
3.1.1 2 Year/2000 Hour Inspection
a.
Make sure the individual modules are properly secured and the
restraining hardware is not damaged or deformed.
b.
Remove the Router Assembly from the mounting brackets. See
Section 4.0 for the Analog Routers and Section 5.0 for the Digital
Router.
c.
Inspect all sheet metal components for damage and corrosion. If
damage or excessive corrosion is found replace parts per Section 4.0
for the Analog Routers and Section 5.0 for the Digital Router.
Corrosion that has penetrated more than .02” is cause for replacement
in machined aluminum components. Corrosion that has penetrated
more than .02” is cause for replacement on sheet metal components.
d.
Inspect all wiring for damage and proper security. Any wires that are
damaged need to be repaired or completely replaced.
e.
Reinstall any removed or replaced parts per applicable portions of
Section 4.0 and Section 5.0 and return aircraft to operational condition.
3.1.2 Special Inspections
a.
In the event that the aircraft experiences a “Hard Landing”, then
conduct the inspection requirements called out in Section 3.1.1.
b.
In the
event that the aircraft experiences a “Lightning Strike”, then
conduct the inspection requirements called out in Section 3.1.1.
3.2
Overhaul Schedule
There is no overhaul schedule for this kit.