background image

Eagle Eye Power Solutions, LLC. 

 

OPERATION 

 

TESTING 208VAC THREE PHASE 

2-1  SETTING  UP  THE  LOAD  BANK  -  Place  the  load  bank  in  an  area  free  from  fuel,  oil,  or  any  other 
flammable  substance. The  load  bank  should  be  positioned  so  that  any  strong  wind  or  air  currents  will 
flow with the air flow of the load bank. 

 

2-2  APPLYING  POWER  -  The  load  bank  should  be  connected  to  the  power  unit  to  be  tested  with  an 
output of 208VAC 3 phase. Make sure that the power unit is off before connecting the cable to the load 
bank. Use L1, L2, L3 and N, the blue and yellow plug, when testing 208VAC 3 phase circuits. Plug the 
power  cable  plug  in  to  the  load  bank.  Turn  on  the  output  of  the  power  unit.  If  the  HI-VOLTAGE  light 
comes  on,  push  the  High  Voltage  reset  button  if  the  meter  shows  120VAC  or  less.  If  the  voltage  is 
above 120VAC, turn off the power being tested and fix the high voltage problem, before using the load 
bank. 

 

2-3 CHECKING THE POWER - check the following: 

A. 

The amber light, “A”, “B”,”C” should be on. 

B. The voltmeter should read 120VAC on 

“A”, “B”, and “C” phase. 

C. The frequency meter should read approximately 60HZ. 
D. The ammeter should read 0A. 
E. The HI-VOLTAGE light should be off. 

 

2-4  APPLYING THE LOAD - If the above steps checked OK, turn on the main switch. The fans should 
start up and the airflow should be as indicated by the airflow arrow. Add the load desired with the rate 
switch. 

A. Step 1 is 

5KW 

B. Step 2 is 

10KW 

C. Step 3 is 

20KW 

D. Step 4 is 

30KW 

E. Rotary Rate Switch 0-5KW 

 

Check to see that the voltage and frequency does not drop beyond acceptable limits under load. Return 
the rate switch to the off position. 

 

2-5  SHUTTING DOWN - After turning the rate off, allow the load bank to cool down before turning the 
power unit off. Turn the power unit off and disconnect the power cable plug.

Содержание LB-60-70

Страница 1: ...gle Eye Power Solutions LLC LB 60 70 LOAD BANK MANUAL CONTAINS OPERATING INSTRUCTIONS PARTS LIST WIRING DIAGRAMS SERVICE INSTRUCTIONS Eagle Eye Power Solutions LLC 4031 W Kiehnau Ave Milwaukee WI 5320...

Страница 2: ...THE POTENTIAL OF DELIVERING A LETHAL SHOCK THIS LOAD BANK SHOULD BE USED ONLY BY TRAINED AND QUALIFIED PERSONNEL THIS LOAD BANK IS DESIGNED FOR TEMPORARY USE ONLY THE LOAD RESISTORS ARE ENERGIZED WHEN...

Страница 3: ...0VAC SINGLE PHASE 2 1 TESTING 240VAC SINGLE PHASE 2 3 TESTING 208VAC THREE PHASE 2 5 PARTS PARTS INFORMATION 3 1 CONTROL PANEL PARTS LAYOUT FIGURE 3 1 3 2 CONTROL PANEL PARTS LIST 3 3 INTERIOR PARTS L...

Страница 4: ...LB 60 70 is rated at 70 KW full load with all four load steps turned on and the rotary rate switch set to 5KW The load steps are 5KW 10KW 20KW and 30KW plus a rotary rate switch with loads of 1 5KW T...

Страница 5: ...Eagle Eye Power Solutions LLC...

Страница 6: ...FREQUENCY METER A 55 65 HZ meter used to measure the frequency of the power unit It should read approximately 60HZ METER SWITCH Switch used to select A B or C phase on the voltmeter RATE SWITCHES Swit...

Страница 7: ...C or less If the voltage is above 120VAC turn off the power being tested and fix the high voltage problem before using the load bank 2 3 CHECKING THE POWER check the following A The amber light A shou...

Страница 8: ...VAC or less If the voltage is above 120VAC turn off the power being tested and fix the high voltage problem before using the load bank 2 3 CHECKING THE POWER check the following A The amber light A an...

Страница 9: ...oltage is above 120VAC turn off the power being tested and fix the high voltage problem before using the load bank 2 3 CHECKING THE POWER check the following A The amber light A B C should beon B The...

Страница 10: ...how a vendor name A part number can be found by first locating the part on a drawing After finding the part use the number to refer to the parts list on the opposite page Each part will have a drawing...

Страница 11: ...Eagle Eye Power Solutions LLC...

Страница 12: ...1 3 MR 60 55 65 HERTZ FREQUENCY METER 1 4 HD 25 HANDLE 2 5 KN 10 POINTER KNOB 2 6 SW 13 ROTARY SWITCH 3 POSITION 1 POLE 1 7 LT 10 115VAC AMBER LIGHT 3 8 SW 31 ROTARY SWITCH 10 POSITION 3 POLE 1 9 SW...

Страница 13: ...Eagle Eye Power Solutions LLC...

Страница 14: ...RESISTOR 100 5W 1 9 CP 22 22UF 150VDC 1 10 RD 10 DIODE 1A 4 11 SW 11 AIR FLOW SWITCH 1 12 LR 08 8 0 RESISTOR 39 13 LR 40 40 RESISTOR 3 14 LR 18 18 8 RESISTOR 6 15 FH 15 SNAP IN FUSE HOLDER 1 16 FS 10...

Страница 15: ...Eagle Eye Power Solutions LLC...

Страница 16: ...3 3 DESCRIPTION NUMBER NUMBER NUMBER VENDOR NO USED 1 FP 57 ALUM FAN PANEL 1 2 TM 20 8 POSITION TERMINAL STRIP V BEAU PRODUCTS 78008 1 3 SW 12 TILT SWITCH 1 4 GL 10 GRILL CHROME 12 5 FN 25 24 VDC FAN...

Страница 17: ...load bank It should however be checked periodically for defective fans burned out light bulbs and defective meters To remove the fan panel remove the screws around the outer edge The meters can be rem...

Страница 18: ...erminal strip coming from the load bank 3 Drill out the rivets holding the fan four on each side 4 Lift up the fan and unplug the wire to the fan Connect the plug to the new fan 5 Rivet the new fan ba...

Страница 19: ...Eagle Eye Power Solutions LLC...

Страница 20: ...Eagle Eye Power Solutions LLC...

Страница 21: ...Eagle Eye Power Solutions LLC...

Страница 22: ...gle Eye Power Solutions LLC Contact EEPS Eagle Eye Power Solutions LLC 4031 W Kiehnau Ave Milwaukee WI 53209 TEL 1 877 805 EEPS 3377 FAX 1 414 962 3660 www eepowersolutions com info eepowersolutions c...

Отзывы: