E2S A131 Скачать руководство пользователя страница 2

                                        

INSTRUCTION MANUAL 

A131 High Level Audible Warning System / Battery backup 

European Safety Systems Ltd.

  

Impress House, Mansell Road, Acton, London W3 7QH    

 

 

[email protected]

     Tel: +44 (0)208 743 8880 

                                                                                                                                                        

www.e2s.com

    Fax: +44 (0)208 740 4200 

Document No. D5423-D5426-IS_Issue_B 12-02-13 
 
 Sheet 

of 

4) Cable 

Selection 

 

When selecting the cable size consideration must 
be given to the input current that the control unit 
draws (see table above) and the length of the 
cable run. 
 

5) Earthing 

 
AC powered control units must be connected to a 
good quality earth. The unit is provided with 
internal earthing terminal which is located next to 
the power terminal (See figure 2).  
 

6)  Horn Location and Mounting 

 

The location of the horn should be made with due 
regard to the area over which the warning signal 
must be audible. The horn should only be fixed to 
services that can carry the weight of the unit. 
 
The horn should be securely bolted to a suitable 
surface using the stainless steel U shaped 
mounting bracket. The angle can then be 
adjusted in the direction that the sound is 
primarily required to cover. This can be achieved 
by loosening the two large bracket bolts in the 
side of the unit, which allow adjustment. On 
completion of the installation the two large 
bracket adjustment bolts on the side of the unit 
must be fully tightened to ensure that the unit 
cannot move in service. 
 

7)  Control Unit Location and Mounting 

 
The location of the control unit will depend on the 
level of customer accessibility required. The 
control unit should only be fixed to services that 
can carry the weight of the unit. 
 
Battery checking and maintenance should also  
be taken into consideration when selecting a 
mounting position. The control unit is mounted via  
the cabinets internal mounting positions using 4 
off suitable screws. 
 
The overall dimensions of this cabinet are 
400mm x 500mm x 210mm, see installation 
figure 1-1. 
 

8) Battery 

Installation 

 

To prevent any problems during transportation, 
the system does not have the battery connected. 
 
Once the control unit has been installed the 
battery should be connected. The loose red cable 
shown should be connected to  the battery 
terminal 4 as shown.  

 

The battery should be routinely checked to 
ensure maximum battery life and correct 
charging.

 

 

 

 
Fig 1-1  Control Unit mounting Installation  

 
 
 
 

 

 

   

1                  2   3                4 

Отзывы: