- 2 -
M965701 Rev. 1.1 (5/17)
1
2
INSTALL VALVE BODY
• Mount VALVE BODY
(1)
to WALL BRACKET
(2)
as shown. Level and tighten SET SCREWS
(3)
to secure
VALVE BODY
(1)
to WALL BRACKET
(2)
.
• Connect HOT water supply to LEFT INLET UNION
(4)
and COLD water supply to RIGHT INLET UNION
(5)
.
Pipe connections are 1/2" NPT. Use sealant or Teflon tape on pipe connections.
Do not solder directly to valve body.
• With valves closed open supply lines and check for leaks. Remove PLASTER GUARDS
(6)
and open both
valves and check for leaks.
• Close both valves and turn off water supplies. Replace PLASTER GUARDS
(6)
and finish wall construction.
• Determine where the finished wall location will be.
This measurement is very important!
Note:
The rough-in measurement
from the finished wall is; 1-9/16" (40 mm) minimum and 2-7/16" (62 mm) maximum. This is a 7/8" (22 mm) tolerance.
See rough-in illustration above.
• Secure WALL BRACKET
(1)
to cross brace of wall structure at required height using six wood screws.
INSTALL WALL BRACKET
WOOD SCREWS
CROSS BRACE
WALL STUDS
1
16" (406 mm)
HOT
COLD
6
6
5
4
2
1
3