Step 1:

 

Position  Barge  Flashing  (102)  on  gable  ends. 
Position  a  Spouting  (A103)  and  rivet  to  the 
Barge  Flashing  at  each  end.  Repeat  with  other 
Spouting.

 

Step 2:

 

Centralise  Barge  Flashing  on  gable  end  and 
rivet in place, one rivet into every second Rib. 
Fit  two  rivets  through  top  of  Barge  into  Rib. 
Repeat  with  other  Barge  Flashing.  Check 
Spoutings  are  straight,  then  rivet  to  Roof  one 
rivet every second Rib.

 

Note: 

MK2 shown

 

Note: 

MK2 shown

 

MK2A FLOOR (Optional)

 

Step 1:

 

Place  shed in final  position.  Check the  diagonal 
measurements  are  the  same  and  the  shed  is 
level before fitting Floor. It is recommended that 
the shed is anchored down with either a Duratuf 
Bolt Down Kit or Duratuf Peg Down Kit depend-
ing on what the shed is sited on.

 

Step 2:

 

Lay a Floor Board on top of Bottom Plates and 
Joist and push up against end wall. Mark out 
where Studs are. Cut checkouts with Electric 
Jigsaw so Floor Board will fit around Studs.

 

Содержание MK2A

Страница 1: ...Quality Built In ASSEMBLY INSTRUCTIONS MK2A BASE SIZE 2545mm x 2545mm...

Страница 2: ...structions Keith s practical tips and tricks will make your assembly experience that much simpler giving you visual guidance through sections that seem tricky on paper and help you achieve a flawless...

Страница 3: ...checklist If you are making your own floor refer to Raised Base Plate section now Do not attempt to build your shed in high winds Beware of sharp edges Protect your eyes and ears Use electric tools wi...

Страница 4: ...ass Louvre Window Frame Glass Window Hardware Pack 2 830m Roof Sheets Security Single Door Hardware Pack Alarm MA20 Shed light Bolt Down Kit Peg Down Kit 1 415m Flat Roof Sheet 175 18 50mm 75mm Floori...

Страница 5: ...LLOW YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW 45 45 785 2545 45 45 45 FRONT WALL 883 45 795 45 785 45 45 1205 2545 45 45 45 BACK WALL 883 45 1205 1900 or 1870 for Raised Base Plate only 1900 o...

Страница 6: ...Pieces of timber from the packaging may be used to tem porarily brace the frame before rolling it over Position 1 205m End Wall Nogs 883m from Top Plate and nail in place If fitting a Kiwi Floor fit...

Страница 7: ...Tack on a wall sheet means to use minimum nails hammered partly in to hold Wall Sheets in position Should a Wall Sheet need to be re positioned the nails can easily be prized out If a window is requir...

Страница 8: ...tack in place Re peat with remaining sheet Step 4 Nailing Off Nail one 30mm Clout each side of the Rib two per Pan into the Top Plates and Bottom Plates Nail Wall Sheets to mid wall Nogs one per pan...

Страница 9: ...ill holes in each corner and nail Win dow Frame to framing using 50mm nails Step 4 If the Window is in the gable end temporarily position the Over Panel above Window Frame Following the same angle as...

Страница 10: ...ttom Plates and hard against Stud Attach Door Jamb Flashing with three rivets into Rib on the outside and three 30mm clouts into studs on the inside Repeat with the other Door Jamb Step 3 Fit Corner F...

Страница 11: ...rackets on the door and align the end of the Door Guide 20mm in from outside of the right hand corner flashing Step 6 Lift the door guide up approximately 3mm so that the Door will Slide freely Pre dr...

Страница 12: ...Back Top Plate Repeat at the front Note The 6 x 50mm Clouts on end ribs are covered by the Barge Flashings Step 2 Position first Roof Sheet centrally over Ridge Beam on the right hand end of shed with...

Страница 13: ...fing screws Screw one 50mm roofing screw into ridge beam through each rib on overlap one screw per sheet Mould the soft edge on the flashing down into the pans of the roof sheet to prevent roof leaks...

Страница 14: ...straight then rivet to Roof one rivet every second Rib Note MK2 shown Note MK2 shown MK2A FLOOR Optional Step 1 Place shed in final position Check the diagonal measurements are the same and the shed i...

Страница 15: ...into Joists Measure and cut Floor Flashing 110 to fit in between Door Jamb Flash ings and nail in place using 50mm Clouts MK2A HASP STAPLE Using six rivets and one 50mm clout attach hasp to Door Jamb...

Страница 16: ...on a purpose built floor concrete cob bles ply etc the Wall Sheets will protrude 20mm below the Base Plate This will stop water flowing in between the Base Plate and Floor The Floor should be made 15...

Страница 17: ...e to hear about your Duratuf experience and why you chose us Further to that we would also love to see a picture or a short video of your shed installed and doing its job so that we can share this wit...

Страница 18: ...e must be carried out in accordance with instructions below Should the cladding fail to perform as specified above the liability of Riverlea Group Ltd shall in all cases be limited to replacing or rep...

Отзывы: