16
ULTRA-SORB MP INSTALLATION, OPERATION, AND MAINTENANCE MANUAL
INSTALLATION
Table 16-1:
O.D. of pipe and tubing
Nom .
Dia .
Standard
pipe
Copper
tubing
SST
tubing
I .D . of
hose
1¼"
(30 mm) 1.660
1.375
-
-
1½"
(38 mm) 1.900
1.625
1.500
1.50
2"
(50 mm) 2.375
2.125
2.000
2.00
2½"
(65 mm) 2.875
2.625
3.000
3.00
Note: Pipe thread and flange tubing adapters
are available from DriSteem.
Piping from a pressurized steam application
STEAM FROM A PRESSURIZED STEAM
Ultra-sorb panels for pressurized steam have a threaded pipe nipple that
extends outside the framework for a steam supply connection. The steam
supply line should be dripped immediately ahead of the steam valve through a
steam trap. See Figure 6-3.
RECOMMENDED TRAP FOR STEAM MAIN DRIP LEG
Use a float and thermostatic (F&T) trap on the steam supply if ≤15 psi and not
lifting condensate. Use an inverted bucket trap if > 15 psi or lifting condensate.
DRIEST STEAM
To ensure driest steam, take humidifier steam off the top of the steam main (not
the side or bottom).