7
Operation:
1. Power: 220V 50HZ
2. Press the power switch to make it switch on (-), and turn the speed control knob, when the
principal machine will begin to rotate.
3. Press (▲ / ▼) keys, the head of principal machine will ascend or descend automatically.
4. After injecting water into the water tank, press the heating key (-) and set the temperature,
which can automatically control the heating process. Heating without water is prohibited.
5. The process of aligning the head angle is as follows: first, loosen the plum blossom knob on
the right side of stand pillar, turn the head of principal machine, and then screw it tightly after
reaching the appropriate angle.
6. After completion of commissioning, power and heating switches will switched to the state of
Off
(0), followed by the unplugging of power plug.