SkyLight 3 Installation Instructions
4
of
6
(765) 987-7999
www.draperinc.com
Draw Cable Routing
The diagram below shows the proper path of the
Draw Cables (see fig 11).
Attaching Draw Cables to Hem Bar
Once the
Draw Cable has been properly routed it must be attached the Hem Bar
with the appropriate amount of tension.
(1)
To ensure proper tension, pull
Draw Cable until the end is in line with the
center of the
Orange Sticker on the Side Channel. To remove slack from the
Draw Cable, rotate the Roller Assembly down (see fig. 12).
(2)
Slide the
Hem Bar to the Draw Cable and insert the Cable into the Hem Bar
Slot (see fig. 13) Slide the Cable along the Hem Bar Slot, toward the Side
Channel, until it stops. This Draw Cable is now properly tensioned.
(3)
Repeat on the opposite side.
Shade Fabric
(attached to Hem Bar)
Hem Bar
in Side Channel
Tensioning Pulley
Draw Cables
Shade Fabric
(attached to Hem Bar)
Over
Tensioning
Pulley
Draw Cables
(one on each side)
End Bracket
Pulleys
End Bracket
Pulleys
Sticker
Hem Bar
in Side Channel
See Attaching Cable
to Hembar Below
Cable Properly Routed- Side View
Before Routing Cable - Side View
Figure
(11)
HEM
BAR
B
Pull Draw Cable until the end is in
line with the center of the Orange
Sticker on the Side Channel
To remove slack from the Draw Cable,
rotate the Roller Assembly Down.
Draw Cable
& Sticker
Draw Cable
& Sticker
Draw Cable
& Sticker
Figure
(12)
HEM
BAR
C
Insert Cable in Hem Bar Slot
and slide Cable all the way
to the end.
D
Repeat on the opposite side.
Figure
(13)