12.1 Checklist for commissioning and inspection
Table 34:
Checklist for commissioning and inspection
Action
OK
Read the operating instructions.
□
Check power supply.
□
Compare the power supply data against the name plate data.
□
Carry out tests to DIN VDE 0100-610.
□
Check the direction of rotation.
□
Check automatic switching:
- Pump changeover
- Additional start-up of the stand-by pump at peak load
- Start-up of the stand-by pump should the duty pump fail
□
□
□
If available: Check settings on motor protection relay.
□
Check the current input of the pump.
□
Check the changeover time from star to delta: required = approx. 3 seconds up to 22 kW power.
□
Thermal circuit breaker connection:
- Ensure that inputs/outputs and serial interface are galvanically isolated from the thermal circuit breaker
inputs.
- If the thermal circuit breaker has no safe isolation from the low-voltage mains, decouple the signals via
coupler modules (accessories).
□
Check correct assignment to pump.
□
Re-tighten the pump terminals.
□
Check the switching mechanisms.
□
Check the start and stop levels.
□
Check messages for correct function and effect.
□
Determine the spare parts requirements, if any.
□
Train operating personnel.
□
Provide new operating manual if necessary.
□