Commissioning the System
CW and DX - Commissioning Procedure
Screens 1 - 5
Screen
Description
3
Low Fan Speed Test
The fan is now energized at the above mentioned
speed. Verify the supply air flow and the acoustics are
correct.
To modify these settings, exit the commissioning
procedure, adjust the program parameters, and run the
commissioning procedure again.
Press the down button to continue.
4
Medium Fan Speed Test
The fan is now energized at the above mentioned
speed. Please verify the supply air flow and the
acoustics are correct.
To modify these settings, exit the commissioning
procedure, adjust the program parameters, and run the
commissioning procedure again.
Press the down button to continue.
5
High Fan Speed Test
The fan is now energized at the above mentioned
speed. Please verify that the supply air flow and the
acoustics are correct.
To modify these settings, exit the commissioning
procedure, adjust the program parameters, and run the
commissioning procedure again.
Press the down button to continue.
CW only - Commissioning Procedure
Screens 6 - 10
Screen
Description
6
Water Temperature Sensor
The water temperature reading is: 49 °F.
The difference between the water temperature and the
inside temperature must exceed the differential setting
to open the valve.
To modify these settings, exit the commissioning
procedure, adjust the program parameters, and run the
commissioning procedure again.
Press the down button to continue.
7
Water Valve Test
The water valve output test is now running and the valve
output is energized. Please verify that the valve is open
and that the supply air is cooler than the room ambient
temperature.
Press the down button to continue.
8
Electric Heater Test
The electric heater output test is now running and the
electric heater is energized. Please verify that the heater
is operating and that the supply air is warmer than the
room ambient temperature.
Press the down button to continue.
CW only - Commissioning Procedure
Screens 6 - 10
Screen
Description
9
Auxiliary (Aux) Heater Test
The aux heater output test is now running and the aux
heater is energized. Please verify that the heater is
operating and that the supply air is warmer than the
room ambient temperature.
Press the down button to continue.
10
Pass Confirmation
Congratulations!
The commissioning procedure is now completed.
Press the down button to continue.
DX only - Commissioning Procedure
Screens 6 - 11
Screen
Description
6
Fault Check
No faults are detected.
If the system has a low-pressure switch, verify that it is
wired and its enable jumper on the main board is cut.
Press the down button to continue.
7
Pump Test
The seawater pump test is now running and the pump
output is energized.
Please verify that the seawater pump is on and pumping
water overboard.
Press the down button to continue.
8
Cool Test
The cooling cycle test is now running and the
compressor should start within 15 seconds.
Please verify that the compressor is operating and
the supply air is cooler than the room ambient air
temperature.
Press the down button to continue.
9
R/C Heat Test
The reverse-cycle heating test is now running and the
compressor should start within 15 seconds.
Please verify that the compressor is operating and the
supply air is warmer than the ambient air temperature.
Press the down button to continue.
10
Auxiliary (Aux) Heat Test
The aux heater output test is now running and the aux
heater is energized.
Please verify that the heater is operating and the supply
air is warmer than the ambient air temperature.
Press the down button to continue.
11
Pass Confirmation
Congratulations!
The commissioning procedure is now completed.
Press the down button to continue.
Содержание MCS-CTRL
Страница 42: ...42 EN Smart Touch Cabin Control...
Страница 43: ...43 EN Smart Touch Cabin Control...