pg. 4
The machine loading-unloading operation can be
carried out:
- using a forklift truck;
- using a hoisting crane.
N.B.: the carrying capacity
of the sling must be at least seven times the total
weight of the machine (if it is made from textile
fibre).
WARNING
: in both cases, the machine must not
be lifted by gripping onto the weakest parts of the
structure (outlet pipes, etc.).
WARNING
:before lifting, ensure that the struc-
ture is balanced
WARNING
: do not make sudden manoeuvres, or
knock the steel parts with the forks of the forklift
truck.
In certain situations, to facilitate transport, the new machine
will be delivered with the transmission separate to the load-bearing structure.
For the
Hidro
version, it is very important that the transmission is in a certain position to
prevent damage to the machine:
2. MACHINE LOADING AND UNLOADING
fig. 7
fig. 6
Before lifting, ensure that the structure is balanced!
Never stand under the suspended load when lifting, transporting or unloading the mixer!
Do not make sudden manoeuvres, or knock the steel parts with the forks of the forklift truck.
Never leave a suspended load unsupervised!