TRX
™
/TRXField
™
and the Circuit Breaker Test Plan
A-28
72A-1898 Rev. A 11/01
Monday
, November 26, 2001 1:09 pm
During the measurement of contact wipe, the measurement starts when
the moving contact makes an electrical contact with the stationary
contact and ends when the moving contact stops (Figure A.30).
Figure A.30 Contact Penetration Measurement Endpoints
Figure A.29 on page A-27 and Figure A.30 show that due to the chamfer
on the moving contact, the mechanical and electrical measurements may
yield different results.
Before the manufacturer’s specification is used, it is important to know
how this value is obtained. If the only specification available is the result
of mechanical measurement, the benchmark for future trending analysis
should be obtained using the TDR9000.
TDR9000
™
TRXField
™
Software and Test Plan Dynamics
The main body of this guide explained the procedures for operating the
TDR9000, including the mechanics for creating or using existing Test
Plans. This section describes the effect that changing Test Plan fields has
on running a test. It does so by relating individual Test Plan items to the
physical components they affect in the field.
TRX
™
/TRXField
™
and the Circuit Breaker Test Plan
The TRX software, comprised of TRX and TRXField, facilitates the
creation of Circuit Breaker Test Plans, analysis of test data, and storage of
Circuit Breaker test data. The TDR9000 operates using only the TRXField
portion of the software. The Test Plan can be created using either of these
programs and is the key to simplifying circuit breaker testing. By creating
a Test Plan, the time-consuming work of entering repetitive circuit
breaker ID information and test parameters is eliminated. Once this data
has been entered, it is saved in the Test Plan on a floppy diskette for reuse
later.
Measurement
starts
Wipe
Содержание TDR9000
Страница 26: ...xxii 72A 1898 Rev A 11 01 Monday November 26 2001 1 09 pm...
Страница 50: ...Step 5 Saving Test Results 1 24 72A 1898 Rev A 11 01 Monday November 26 2001 1 09 pm...
Страница 98: ...3 28 72A 1898 Rev A 11 01 Monday November 26 2001 1 09 pm...
Страница 200: ...Disconnecting After the Test 4 102 72A 1898 Rev A 11 01 Monday November 26 2001 1 09 pm...
Страница 362: ...B 34 72A 1898 Rev A 11 01 Monday November 26 2001 1 09 pm...
Страница 388: ...D 6 72A 1898 Rev A 11 01 Monday November 26 2001 1 09 pm...
Страница 392: ...E 4 72A 1898 Rev A 11 01 Monday November 26 2001 1 09 pm...
Страница 394: ...F 2 72A 1898 Rev A 11 01 Monday November 26 2001 1 09 pm...
Страница 442: ...I 32 72A 1898 Rev A 11 01 Monday November 26 2001 1 09 pm...
Страница 454: ...I 12 72A 1898 Rev A 11 01 Monday November 26 2001 1 09 pm...