Sweep Frequency Response Analyzer (SFRA) User Guide
3-12
72A-2570-01 Rev. K 07/2011
7.
When you are satisfied with the test results:
a. Disconnect the test lead clamps from each other.
b. Disconnect the reference ground clamps from each other.
8.
“Step 2: Ground the Transformer” on page 3-12
.
Step 2: Ground the Transformer
Each time the SFRA test leads are connected, disconnected, or moved, apply
temporary static-discharge grounds to:
•
The bushings to which the SFRA test clamps will be applied
and
•
Any bushings to which jumpers will be applied
To ground a transformer for SFRA testing:
1.
Open the switches to de-energize the transformer and disconnect it from
the rest of the substation (
).
Figure 3.18 De-energized and Disconnected Transformer
2.
Ground all conductor or bus still connected to the transformer terminals
outside of the transformer bushings and windings (
Figure 3.19 Grounded Transformer
Содержание SFRA
Страница 12: ...Sweep Frequency Response Analyzer SFRA User Guide xii 72A 2570 01 Rev K 07 2011...
Страница 14: ...Sweep Frequency Response Analyzer SFRA User Guide xiv 72A 2570 01 Rev K 07 2011...
Страница 24: ...Sweep Frequency Response Analyzer SFRA User Guide 2 4 72A 2570 01 Rev K 07 2011...
Страница 56: ...Sweep Frequency Response Analyzer SFRA User Guide 3 32 72A 2570 01 Rev K 07 2011...
Страница 78: ...Sweep Frequency Response Analyzer SFRA User Guide 5 18 72A 2570 01 Rev K 07 2011...
Страница 98: ...Sweep Frequency Response Analyzer SFRA User Guide A 20 72A 2570 01 Rev K 07 2011...
Страница 110: ...Sweep Frequency Response Analyzer SFRA User Guide C 6 72A 2570 01 Rev K 07 2011...
Страница 116: ...Sweep Frequency Response Analyzer SFRA User Guide D 6 72A 2570 01 Rev K 07 2011...