Instruction Manual
14
3. BOILER INSTALLATION
The boiler must be installed by an authorised service company and according to local regulations. Installation of the boiler
must be done so that its position is unaffected by any tension arising from increased work volumes (noise, vibrations, and
stresses). After installation is complete, check the tightness of all gas, water, and flue gas connections in the system.
3.1 REQUIREMENTS FOR BOILER INSTALLATION
3.1.1 The installation regulations for the water, gas and the flue gas system
The use of gas appliances, flues and ventilation should be consistent with AS/NZS 5601 and local requirements relating to
the technical conditions of their use in residential buildings.
Before installing the boiler, check whether the consent from the District Department of Gas, Chimney Sweep Company and
Building Administration must be obtained.
NOTE!
Gas appliances supplied with liquefied gas must not be installed in rooms with a floor below ground level.
If liquefied gas 3B/P is used, it is recommended that the room temperature where the gas cylinder will be operated is not
less than 15ºC.
NOTE!
The main socket through which the boiler is powered must comply with PN-IEC-60364-6-61:2000
3.1.2 Regulations related to the room
Requirements for premises where gas appliances are installed should be in accordance with local regulations. The room
where the boiler is to be installed should meet the air supply and venting system requirements for gas combustion,
according to regulations. In addition, the room’s temperature should be higher than 6ºC and the location of the ventilation
system should not cause the freezing of water.
The room should also be free from dust and aggressive
gases. It is forbidden to install the boiler in laundry rooms,
drying rooms, or rooms where varnish, cleaners, solvents,
and sprays are stored.
The device covered by this instruction manual has a Zone
1 degree of electrical protection provided by the housing
- IPX4D. A boiler equipped with a power cord and plug can
be installed in Zone 2 or further - but must not be installed
in Zone 1, unless it is permanently connected to a power
source, in accordance with HD 60364-7-701.
3.1.3 Requirements for electrical installation
The boiler has been designed for operation with single-phase alternating current with a rated voltage of 230 V/50 Hz.
The boiler has been designed as a “class I“ device and must be connected to an electrical outlet with ground terminal in
accordance with PN- IEC 60364-4-41.
Fig. 3.1.2.1. The zones dimensions in areas containing a bath or shower with a pool
Be careful to connect the power cord correctly. If done incorrectly:
•
the boiler enters into failure state
•
E01 (error) will show on the display (see section 5.8.3)