4.1 Connect one lead from the “+” lead of the DC source (See Item 3.1) to the “20A” terminal of the 

first multi-meter DVM1 (See Item 3.3). Then connect one lead from the “Common” of the DVM1 
to the “Vin” pin of the Evaluation Board. DVM1 is used to measure the input current.   

 

4.2 Connect one wire from the “-” lead of the DC source (See Item 3.1) to the “GND“ pin of the

Evaluation Board.  Note: Use stranded leads at least equivalent to 14 AWG for all connections 
in sections 4.1 and 4.2. The leads should be twisted to reduce noise coupling.  

 

4.3 Connect the plus “+” and minus “-“ connection leads from a second multi-meter (See Item 3.3) 

to the “SVin” and “SGND” pins on the Evaluation Board. This multi-meter is designated DVM2. 
DVM2 is used to measure the input voltage. 

 

4.4 Connect the plus “+” and minus “-“ connection leads from the third multi-meter (See Item 3.3) to 

the “SVOUT” and “SGND” Pin on the Evaluation Board. The multi-meter is designated DVM3. 
DVM3 is used to measure the output voltage. 

 

4.5 Connect a BNC cable (length less than 20 inches/500mm) from BNC1 of the Evaluation Board 

to Channel 1 of the oscilloscope (See Item 3.2). This cable is used to measure the input 
voltage (between SVIN and SGND). 

 

4.6 Connect a BNC cable (length less than 20 inches/500mm) from BNC2 of the Evaluation Board 

to Channel 2 of the oscilloscope (See Item 3.2). This cable is used to measure the output 
voltage (between SVOUT and SGND). 

 

4.7 Connect the positive and negative power leads of the electronic load (ensuring correct polarity), 

or an appropriate resistive load to the Evaluation Board output terminal pin (“Vout” for positive 
power lead and “SGND” for the negative power lead). 

 

4.8 Connect one lead from the “+” lead of the DC source (See Item 3.5) to the “12Vcc” on the 

Evaluation Board. Then connect one lead from the “-” of the DC source (See Item 3.5) to the 
“12VGND” on the Evaluation Board. 

 

5.0 Thermal Management of the Converter 

 

It is imperative that sufficient airflow needs to be provided to the converter at all times during all 
portions of testing. Please refer to the applicable data sheet for the proper cooling and derating 
necessary conditions to obtain accurate results when testing the converter. 
 
 
 

 

Содержание DEP-008 A

Страница 1: ...a myriad of standard protection features This document guides the user through the evaluation procedures to qualify a POL module The data shown in this Evaluation Procedure is for the SIP Package Type...

Страница 2: ...3 3 Digital multi meters one with 20A range and ideally all with 4 1 2 digit resolution DVM1 DVM2 and DVM3 Zentech 2041 or equivalent 3 4 An electronic load Chroma 63030 or equivalent 300W approximate...

Страница 3: ...BNC cable length less than 20 inches 500mm from BNC1 of the Evaluation Board to Channel 1 of the oscilloscope See Item 3 2 This cable is used to measure the input voltage between SVIN and SGND 4 6 Con...

Страница 4: ...r of the power module to determine that the correct module is being evaluated Note DNS04S0A0S06P A would denote the SMT package while DNS04S0A0R06P A would denote the SIP package This Evaluation Board...

Страница 5: ...he converter requires a margin trim up set the SW3_4 to ON position Please refer to the SW3 Function table SW3 Function table Subdivide switch No Function SW3_1 Voltage trim up SW3_2 Voltage trim down...

Страница 6: ...4 Test the input under voltage function while observing DVM2 DVM3 and channel 1 of the oscilloscope Increase the input voltage until the output of the converter reaches the appropriate value This wil...

Страница 7: ...voltage and temperature remain constant Test 1 Turn on the fan 2 Set the input voltage to the desired operating level while monitoring DVM2 3 Set the switch SW2 to the converter ON 4 Adjust the output...

Страница 8: ...program the output voltage of the DNS04 module to 1 8Vdc below is the calculation of Rtrim 15004 5110 7525 0 8 1 21070 set R The table 1 provides the Rset value required for some standard output and t...

Страница 9: ...nge of the operating load range please refer to the data sheet for the detailed specification 2 Output Voltage Set Point Adjustment by external voltage source For DNS series trim to Vo set using an ex...

Страница 10: ...im up and Rmargin down is for trim down Please refer to the data sheet and Evaluation Board Schematic for the detailed information A software tool for voltage margining calculation is available to ask...

Страница 11: ...al start up is implemented by connecting the power good signal PWRGD pin of PS1 to the TRACK pin of PS2 with a resistor capacitor RC circuit The waveforms of power up and down are in Figures 4 and 5 I...

Страница 12: ...termine the tracking method that is implemented To simplify the tracking design set initial value of R2 equal to 20K at internal circuit and set resistor R1 for different tracking method Figure 6 show...

Страница 13: ...he PS2 Voset PS2 3 3V R1 is calculated as follows K K R 75 55 20 32 1 32 1 7 1 3 3 1 Figure 7 Ratio metric tracking Power up Figure 8 Ratio metric tracking Power down For Ratio Metric applications tha...

Страница 14: ...The objective is to minimize the voltage difference between the power supply outputs during power up and down The waveforms of power up and down are showed in Figures 13 and 14 For type A DNXXX0A0XXX...

Страница 15: ...tart up when VoPS2 tracks the VoPS1 only for type C R1 R2 TRACK VoPS1 PS2 VoPS2 PS1 Vin Vin ENABLE ENABLE To Tracking circuit 20K 30 1K Figure 12 PS1 and PS2 track output voltage Simultaneous start up...

Страница 16: ...absolute maximum voltage cannot over the Vin 5 For type A When Tracking is unused put R1 equal to 1K and connect TRACK pin to Vcc For type C When Tracking is unused put R1 equal to 30 1K and connect...

Страница 17: ...ltage 2 Turn on module by using the Enable on off Test Turn on the module by using the external switch 1 Turn on the fan 2 Turn on the input power supply and set it to the desired operating point 3 Se...

Страница 18: ...the ratio of total output power to the input power It is typically measured at full load and nominal input voltage Test 1 Turn on the fan 2 Set the enable switch SW2 to the converter ON 3 Adjust the i...

Страница 19: ...Appendix A Evaluation Board Schematic 19...

Страница 20: ...x 886 3 4513485 Email DCDC delta com tw Warranty Delta offers a two 2 year limited warranty Complete warranty information is listed on our web site or is available upon request from Delta Information...

Отзывы: