Safety Shield Bracket Installation
1. Safety Shield Brackets are to be installed at the outside
corners of each module (4 per module). Consult below
detail for locations. Use 3/8-16 x 1.25" hardware to install
brackets. Consult “Hardware Torque Requirements”
(pg 5) for proper torque values.
2. Module layout should be compared to system layout
diagram and all hardware should be checked for proper
torque before proceeding. Consult “Hardware Torque
Requirements” (pg 5) for proper torque values.
ELECTRICAL CONNECTION
Follow all safety requirements as detailed in “Safety
Precautions” section prior to working on any electrical
connections.
Some installations may require the terminal plates to be in
close proximity of each other. It is recommended that the
terminal plate assembly installations be completed prior to
installing the inter-cell connections. This practice will reduce
the risk of a possible electrical short from damaging the entire
battery system.
TERMINAL ASSEMBLY
Top Termination
Consult system layout diagram for termination locations.
1. Install terminal plate bracket to the top of the module.
Slide clip onto back of channel at hole locations.
Use 3/8-16 x 1.25" hardware. Install loosely for
future alignment.
Top Shield Bracket Installation
Center Shield Bracket Installation
9
Bottom Shield Bracket Installation
Bottom Retainer Bar