10
6. Cable tie power lead from pump to
pipework and bundle excess cable to
base of the Evolution MkII.
7. Arrange pump so that stand pipe
aligns with Evolution MkII inlet at
base of primary filter chamber.
8. Remove primary filter lid and filter
from the Evolution MkII housing to
expose four Phillips head screws in
chamber base.
9. Fasten Evolution MkII to tank top
using self drilling sheet metal screws
using the 7 locations provided.
10. Fasten the four screws in the base
of the primary chamber in order to
clamp stand pipe in position. Ensure
screws are tight by repeating the
tightening pattern.
11. Reinstall the primary filter and lid.
12. Connect Mains and outlet plumbing
to Evolution MkII ensuring correct
orientation. If plumbing fit out is
incorrect, the use of flexible hoses
is suggested to connect to the
Evolution MkII.
13. Open Mains water valve and check
for leaks.
14. Switch on power to RainBank and
check for flashing green light – light
will flash ten times as it boots up.
15. Open a tap downstream of RainBank
to clear lines of air and check for
leaks. Requires a flow rate of at least
10 litres in 1 minute to expel air.
16. Press manual override button on top
of RainBank to start pump and flush
air from rainwater lines. There must
be rainwater inside the tank – this is
an important part of commissioning
the system.
17. Close tap and check for leaks.
pipe clamp
screws