Illustration 3.4 Installed PV Power
Enter the amount of installed PV power for each of the PV
inputs. When two or more PV inputs are connected in
parallel, each PV input in the parallel group must be set to
the total amount of PV power installed to that group
divided by the number of parallel inputs. See
Table 3.1
.
Illustration 3.5 Select Country
Select the country in which the inverter is installed. Press
'
▼
' to scroll down the list of countries. To select a country,
press 'OK'.
Illustration 3.6 Select Grid Code
The display will now show “Select grid”. The grid code is
set to “undefined” at initial start-up. To select grid code,
press 'OK'. Press ‘
▼
’ to scroll down through the list of
countries. Select the grid code for the installation by
pressing ‘OK’. It is very important that the correct grid
code is chosen.
Illustration 3.7 Confirm Grid Code Selection
Confirm the choice by selecting the grid code again and
press 'OK’. The settings for the chosen grid code have now
been activated.
Start-up and Check of Setti...