4.2.2
Filling
122
121
80
B
C
A
94
111
112
100
E
D
80
Shut-off valve
94
Filling device
100
Safety valve
121
Brine in
122
Brine out
A
Shut-off valve (part of 94)
B
Shut-off valve (part of 94)
C
Dirt strainer with shut off valve (part of 94)
D
External container
E
External pump
1. Set the heat pump to OFF on the control panel.
2. Mix water and antifreeze to the correct freezing point in an external container .
N
Ensure that the external container contains the requisite
amount of brine.
3. Use a refractometer to check the freezing point, -17±2°C.
4. Use an external pump to fill the brine system. Connect the pressure side of the pump to the filler cock.
5. Close the shut-off valve on the filler cock.
6. Open the suction valve on the filler cock and the return valve on the brine system.
7. Connect a transparent hose to the filler cock. The hose should discharge into the external container.
8. Open the return valve on the filler cock.
9. Start the external pump and fill the brine circuit .
N
Allow the external pump to run until the manual test of the
brine pump is complete. See "Manual test".
Check the brine level in the external container at regular inter-
vals.
Commissioning
DHP-H Varius Pro+/DHP-L Varius Pro+
Danfoss Heating Solutions
VIJSG202
13
Содержание DHP-H Varius Pro+
Страница 1: ...MAKING MODERN LIVING POSSIBLE Commissioning DHP H Varius Pro DHP L Varius Pro www heating danfoss com...
Страница 34: ...Commissioning DHP H Varius Pro DHP L Varius Pro VIJSG202 Danfoss Heating Solutions 34...
Страница 35: ...Commissioning DHP H Varius Pro DHP L Varius Pro Danfoss Heating Solutions VIJSG202 35...