5 Commissioning
5.1.1 Commissioning
Prior to initial switch-on of the filter module check the wiring for completeness, short-circuit and earth fault.
If the wiring is not correct, a non-intended operation of controller and/or filter module is possible.
First powering up
1.
Switch on mains supply :
- The filter module is ready for operation at once.
2.
Check the readiness of the frequency converter:
- Proceed in accordance with the operating instructions of the frequency converter.