Installation Module
►
Undo the four screws on the duct cover until they are
loose in their anchor points.
►
Then remove the cover.
►
To install modules always use the first empty duct from the
left-hand side of the module rack.
Before installing the modules check whether they are integrated in the network via DHCP or which IP addresses are available.
NOTICE
To prevent network conflicts the IP address or DHCP must be configured after you
install each module.
A free duct should be available for every module you have ordered.
►
Remove the duct covers from the required ducts.
Start on the left-hand side of the module rack. The modules must later be installed in sequence from left to right.
WARNING
Do not reach into the open housing of the module rack. Do not insert any objects.
The module rack is already live. This means that there is a risk of electric shock.
NOTICE
Damage to components at risk from electrostatic discharge caused by touching them.
Ensure that you are electrostatically discharged (earthed) before you touch the mo-
dule.
Wear suitable ESD shoes or an earth strap.
►
Insert the module into the guide rails (top and bottom).
►
Carefully slide the module into the module rack.
►
Ensure that you slide it straight. Do not use any force.
The module is inserted correctly when it has been fully slid in and
engaged.
►
The front cover of the module must be flush with the
edge of the module rack housing.
The module will now already be powering up.