background image

9.  Once box is level 

measure the 

distance away 

from pool headers 

so they are the 

same either side 

within a couple of 

millimetres.

5.  Level these slabs so they are approx. 

512-515mm (BGB) or 356-360mm (BGB 

Small) below the finished height of paving or 

concrete. Place spirit level on pool headers 

and lay across the trench propping the other 

end up so spirit level is level, using the level 

measure down to slabs to obtain correct 

depth of slab, use rubber mallet to tape 

down to bed slab in.

7.  Once blue metal is 

down you are ready 

to place box into 

hole. Carry box to 

the trench edge, 

place rope or straps 

under each end of 

box and use these 

to lift and lower into 

hole.

11. Once box is level and square to the pool start 

back filling with soil and washing in soil as 

you go to eliminate any air pockets around 

the box.

13. To prevent lid from decolourisation, protect 

lid from concrete slurry, sealers, acids and 

chlorine.

6.  Once both slabs are in place and at correct 

level place for sufficient drainage, blue metal 

or aggregate along the trench making sure 

you do not exceed more than 50mm above 

the slab height, for boxes with a centre brace 

or braces leave a small amount out so brace 

doesn’t touch the blue metal. 

 

NOTE: Take note of site and soil drainage 

requirements. Extra (sub soil) drainage may 

be required to take water away from the void 

of the BGB. If there is not sufficient drainage 

the BGB will fill with water.

8.  With box in the hole 

and end braces are 
sitting on concrete slabs 
level box up to required 
height via the 4 bolts 
inside the box, screw all 
4 down so they touch 
the concrete slabs and 
then every 1 turn gives 
you approx. 1mm of lift. 
Make sure cover does 
not touch bolt head.

10. Place supplied 

spacers between lid 

and front extrusion 

on the box prior to 

back filling

12. Leave spacers in place until paving or 

concrete has been completed, this will 

prevent any extra pressure caused from 

walking around the box or compaction 

pushing walls in too far. 

14. The roller Bevel Gearbox drive mechanism 

can be installed either side of unit. To change 

ends simply unbolt the 8mm mounting bolts 

(through square tube) to remove and turn the 

roller around