Commissioning
Installer reference guide
58
4MWXM-A9
R32 Split series
4P708645-1 – 2022.09
12 Commissioning
NOTICE
General commissioning checklist.
Next to the commissioning instructions in this
chapter, a general commissioning checklist is also available on the Daikin Business
Portal (authentication required).
The general commissioning checklist is complementary to the instructions in this
chapter and can be used as a guideline and reporting template during commissioning
and hand-over to the user.
In this chapter
12.1 Overview: Commissioning
This chapter describes what you have to do and know to commission the system
after it is installed.
Typical workflow
Commissioning typically consists of the following stages:
1
Checking the "Checklist before commissioning".
2
Performing a test run for the system.
12.2 Precautions when commissioning
INFORMATION
During the first running period of the unit, the required power may be higher than
stated on the nameplate of the unit. This phenomenon is caused by the compressor,
that needs a continuous run time of 50 hours before reaching smooth operation and
stable power consumption.
NOTICE
ALWAYS operate the unit with thermistors and/or pressure sensors/switches. If NOT,
burning of the compressor might be the result.
NOTICE
ALWAYS complete the refrigerant piping of the unit before operating. If NOT, the
compressor will break.
Содержание Multi+ R32 Split Series
Страница 1: ...Installer reference guide R32 Split series 4MWXM52A2V1B9...
Страница 31: ...6 Unit installation Installer reference guide 31 4MWXM A9 R32 Split series 4P708645 1 2022 09...
Страница 77: ......
Страница 78: ......
Страница 79: ......
Страница 80: ...4P708645 1 2022 09 Copyright 2022 Daikin Verantwortung f r Energie und Umwelt...