14 BEFORE STARTING
The unit should not be started, not even for a very short period, before the following pre-commissioning checklist is filled out completely.
Table 11-Pre-commissioning checklist
Tick/when
checked
Standard stops to go through before starting the unit
1
Check for
external damage
.
2
Install
main fuses, earth leak detector
and
main switch
.
Recommended fuses: aM according to
IEC
standard
269-2.
Refer to the wiring diagram for size
.
3
Supply the main voltage and check if it is within the
allowable ±10% limits of the nameplate rating.
The electrical
main power supply
must be arranged so, that
it can be switched on or off independently of the electrical
supply to other items of the plant and equipment in general.
Refer to the wiring diagram, terminals N,PE, L1, L2 and L3.
4
Supply water to the evaporator and verify if
waterflow
is
within the limits as given in the table under "Water charge,
flow and quality
”.
5
The piping must be completely
purged
. See also chapter
"Checking the water circuit
”.
6
Connect the
flow switch
and
pump-contacts
, so that the unit
can only come in operation when the water
pumps are
running and the waterflow is sufficient. Make sure a water
filter is installed before the water inlet of the unit.
7
Connect the field wiring for
pumps start-stop
.
8
Connect the field wiring for
remote control
.
NOTE:
1.
Try to reduce the drilling in the unit to a minimum. If drilling is not preventable, remove the iron filling thoroughly in order
to prevent surface rust!
2.
It is necessary to read the operation manual delivered with the unit before operating the unit. It will contribute to
understand the operation of the unit and its electronic controller.
3.
Verify on the wiring diagram all electrical mentioned above, in order to understand the operation of the unit more deeply.
4.
Close all switch box doors after the installation of the unit.
I do confirm having executed and checked all the above mentioned above.
Date