11
|
Commissioning
Installer reference guide
163
ERLA EHFZ03S18DJ3V
Daikin Altherma 3 R F
4P596821-1B – 2021.10
11.4.4 To perform an actuator test run
Perform an actuator test run to confirm the operation of the different actuators.
For example, when you select
Pump
, a test run of the pump will start.
Purpose of the actuator test run is to confirm the operation of the different
actuators (e.g., when you select pump operation, a test run of the pump will start).
Prerequisite:
Make sure that the leaving water temperature home page, room
temperature home page, and domestic hot water home page are turned OFF.
1
Set the user permission level to Installer. See
"To set the user permission level
2
Go to [A.7.4]: >
Installer settings
>
Commissioning
>
Actuator
test run
.
3
Select an actuator and press .
Example:
Pump
.
4
Select
OK
and press .
Result:
The actuator test run starts. It automatically stops when finished. To stop it
manually, press , select
OK
and press .
11.4.5 Underfloor heating screed dryout
The underfloor heating (UFH) screed dryout function is used for drying out the
screed of an underfloor heating system during the construction of the building.
The UFH screed dryout function can be executed without finishing the outdoor
installation. In this case, the backup heater will perform the screed dryout and
supply the leaving water without heat pump operation.
If the outdoor unit is not yet installed, connect the main power supply cable to the
indoor unit via X2M/30 and X2M/31. See
"9.3.1 To connect the main power
94].
INFORMATION
▪
If
Emergency
is set to
Manual
([A.6.C]=0), and the unit is triggered to start
emergency operation, the user interface will ask confirmation before starting.
The underfloor heating screed dryout function is active even if the user does NOT
confirm emergency operation.
▪
During underfloor heating screed dryout, pump speed limitation [9‑0D] is NOT
applicable.
NOTICE
The installer is responsible for:
▪
contacting the screed manufacturer for the maximum allowed water
temperature, to avoid cracking the screed,
▪
programming the underfloor heating screed dryout schedule according to the
initial heating instructions of the screed manufacturer,
▪
checking the proper functioning of the setup on a regular basis,
▪
performing the correct program complying with the type of the used screed.
Содержание EHFZ03S18DJ3V
Страница 1: ...Installer reference guide Daikin Altherma 3 R F ERLA03DAV3 EHFZ03S18DJ3V...
Страница 211: ......
Страница 212: ...4P596821 1B 2021 10 Copyright 2019 Daikin Verantwortung f r Energie und Umwelt...