- 14 - 

 

 

Figure 35 - Wiring Diagram with Neutral 

 

Heat  Wheel

  –  Ensure  the  heat  wheel  can 

rotate freely by hand. 

Heat Pipe

 – Ensure installations are as per 

manufacturer recommendation. 

 

6.2 Start-up Check 

 

Competent,  well-trained  personnel  must 
be employed in the following operations to 
ensure Safety Rules and Regulation being 

adhered to at all time. 

 

 

IMPORTANT 

FAILURE  TO  PROVIDE  MOTOR 

OVERLOAD  PROTECTION  COULD 

RESULT  IN  MOTOR  DAMAGE. 

CONNECT  THE  MOTOR  TO  AN 

OVERLOAD  PROTECTIVE  DEVICE 

THAT  IS  RATED  IN  COMPLIANCE 

WITH THE APPLICABLE CODE. 

 

a.

 

Check the rotation of the fan impeller. 

If the fan rotates in opposite direction 
from  desire,  reverse  any  two  phase 
connection at motor terminal. 

b.

 

Check  that  there  is  no  unusual  noise 
or  vibration.  Stop  and  investigate  if 

found. (refer to section 8) 

c.

 

Measure  the  voltage  and  drawn 

current  of  the  motor.  The  drawn 
current  must  not  exceed  the  full  load 
current 

mentioned 

at 

motor 

nameplate. 

 

6.3 After first 48 hours of operation 

 

a.

 

Make  sure  complete  isolate  the 
Electrical source. 

b.

 

Re-check  and  Re-tension  the  drive 
belts due to stretch. 

c.

 

Check and adjust the pulley alignment 

to ensure the motor fixing is properly 
secure. 

d.

 

Check  all  bearing,  wheel  bolts  &  nuts 
and sheave set screws (or cap screw) 
are in secure position. 

CAUTION 

HIGH  AIR  TEMPERATURE  IN  FAN 

SECTION  CAN  CAUSE  MOTOR 

OVERHEAT  AND  DAMAGE.  ON 

DRAW-THROUGH  AIR  HANDLERS, 

ADJUST  THE  DISCHARGE  AIR 

TEMPERATURE  OF  THE  HEATING 

SECTION  NOT  TO  EXCEED  104

0

(40

0

C).  

 

6.4 Fan Operating Limits 

 

The fan operating limits for forward curve 

and  airfoil fan are shown  on the  Table  3. 
Total  static  pressure  should  be  limited  to 

1000 Pa for forward curve and 1500 Pa for 
backward curve/airfoil fan.

  

 

Table 3 - Fan Operating limits 

Blower 

Size 

Forward Curved 

Backward 
Curve/Airfoil 

Max. 
RPM 

Max. 
kW 

Max. 
RPM 

Max. 
kW 

200 

3800 

5700 

225 

3400 

5400 

250 

2600 

4400 

280 

2400 

3900 

315 

2100 

3500 

355 

1900 

3100 

400 

1700 

2700 

450 

1400 

10 

2500 

11 

500 

1200 

11 

2200 

11 

560 

1100 

15 

1900 

15 

630 

900 

15 

1700 

15 

710 

850 

25 

1500 

30 

800 

750 

25 

1350 

30 

900 

650 

30 

1150 

35 

1000 

600 

30 

1050 

35 

 

6.5  Installation  of  VRV  AHU  Control 

Box (EKEQ) 

 

For  installation  VRV  AHU  Control  Box, 
please  refer  to  the  Installation  And 

Operation  Manual  in  VRV  ED  or  refer  to 
manufacturer for advices. 

 

6.6 MicroTech III Commissioning 

 

MicroTech  III  is  an  option.  For 

commissioning  of  MicroTech  III,  please 
refer  to  the  MicroTech  III  Commissioning 
Manual  in  VRV  ED  or  refer  to 
manufacturer for advices. 

 

7. Maintenance 

 

7.1 Fan / Motor 

 

Check  for  soiling,  corrosion,  damage  and 

tendency of excessive vibration.  
Check  that  all  bolts  and  nuts  and  flexible 
connections are securely fixed. 

Содержание AHUR VRV AHU

Страница 1: ...LATION OPERATION MAINTENANCE VER O AHU01 DEC20 15 The design and construction are subject to change without any notice for future improvement MODELS DM AHU DS AHU AHUR VRV AHU Double Skin Modular Air...

Страница 2: ...rtificate which is determined by International National or Local Codes and Regulation Place of service should be equipped with the necessary protective equipment which provide safe maintenance 1 4 Uni...

Страница 3: ...truck 4 Storage For external storage prior to installation the units must be protected from dust rain constant sun exposure and rodents Although covered in shrink wrapped plastic sheeting this is not...

Страница 4: ...carefully assembled to desired unit arrangement The air handling units are design to use section joint brackets to combine two sections Section joints for cabinet and base frame are shown in Figure 5...

Страница 5: ...on joint WARNING CABINET SECTION JOINTS ARE NOT INTENDED FOR LIFTING PURPOSE AND PULLING CABINET FROM A DISTANCE TO JOIN SECTION TOGETHER When the cabinets are penta post to penta post arrangement or...

Страница 6: ...hipped out from factory See Figure 15 Figure 14 Restrained Spring Isolator Figure 15 Removing of U Shaped Plate 5 5 Arrangement VRV AHU Control box and expansion valve kit are installed on the air han...

Страница 7: ...joints or flexible fittings are to be provided in all piping connections particularly those adjacent to heating source to absorb expansion and contraction strains Failure to comply will result in dama...

Страница 8: ...valve and not to a common header When two or more coils are connected to a common suction line never place the bulb on the common line Thermostatic expansion valve is to be equipped with external equa...

Страница 9: ...r control refer to the VFD manual for wire size and requirements Figure 22 3 phases motor connection diagram 5 7 2 Motor Cabling Motor wiring must go downward from motor terminal box to prevent conden...

Страница 10: ...he diameter of smaller pulley Table 2 Adjusted Pitch Diameter Model VPT100Z1 VPT120A1 A2 VPT139A1 A2 VPT156A1 A2 VPT177A1 A2 VPT178B2 Max Pitch mm 96 114 4 133 4 150 4 171 4 171 Min Pitch mm 82 9 96 1...

Страница 11: ...ee Table 2 Figure 27 When the required diameter is obtained adjustable flange is locked by tighten the four clamp screws To get the same diameter in the two grooves of pulleys screw the two mobile fla...

Страница 12: ...out Notes 1 Elbows should not be closer than 2 1 2 times the Duct Equivalent Diameter Refer to Formula 1 2 Dampers should be placed at least fan diameters downstream of the fan discharge Formula 1 Duc...

Страница 13: ...ther For DX coils it is advisable that the refrigerant is to be pumped into the condenser If this is not possible refrigerant shall be purged out WARNING DO NOT HEAT ANY PART ON DX COIL IF REFRIGERANT...

Страница 14: ...20mm 6 1 5 Coils Check the pipe work to coil is correctly connected and the fins are free from foreign matter or damage Check that the condensate drain is trap Ensure good sealing of silicon around th...

Страница 15: ...or cap screw are in secure position CAUTION HIGH AIR TEMPERATURE IN FAN SECTION CAN CAUSE MOTOR OVERHEAT AND DAMAGE ON DRAW THROUGH AIR HANDLERS ADJUST THE DISCHARGE AIR TEMPERATURE OF THE HEATING SE...

Страница 16: ...ling heating efficiency Dry cleaning is done by using a powerful vacuum cleaner on the dust accumulated side If coil is very dirty coils need to be removed for wet cleaning by trained personnel Ensure...

Страница 17: ...IR VELOCITY SHOULD NOT BE LOWER THAN 2 0 m s 7 7 Heat Wheel Heat Pipe The unit should be maintained in line with the manufacturer recommendation Please refer installation and maintenance manual for de...

Страница 18: ...not evenly supported on foundation j Fan assembly s tolerance is out of range a Consult manufacturer b Remove transport bracket c Check pulley alignment d Re tension belts e Replace vibration isolato...

Страница 19: ...he heat wheel baffle top 8 Assembled back the remaining panels 9 2 AHU Water Quality Water quality requirements Water softening treatment must be given in advance to prevent scaling in the heat exchan...