24) Verify primary control operation and safety features according to procedure outlined in the instructions furnished with
control.
25) Check pressure limit control operation. Jump thermostat terminals and allow burner to run until boiler pressure exceeds
cut-in pressure plus the differential. The burner should shut down.
26) Check low water cut-off operation. With the thermostat still jumped, fire the boiler and crack the boiler drain valve so that
water is slowly drained from the boiler. Confirm that the burner shuts down before the water level drops below the bottom of
the sight glass. 

Do not permit the boiler to fire without water visible in the sight glass

. Add water to the boiler and

confirm that the burner restarts. Remove thermostat jumper and reconnect thermostat upon check completion.
27) After the boiler has operated for approximately 30 minutes, check the boiler and heating system for leaks. Repair any
leaks found at once.
28) After the above checks have been completed, leave thermostat(s) at desired setting. Leave all instructions provided with
the boiler with owner or in boiler room, displayed near boiler.
29) After new boiler has been installed and put into continuous operation for several days, clean the boiler of oil, grease,
sludge, and other contaminants that may have been present in existing piping. This will prevent unsteady water line and water
carry over into supply main. The boiler boil-out should be done as follows:

a) Turn off the burner.
b) Drain water from boiler until about one inch of water is visible in gauge glass.
c) Run a hose or temporary piping from the boiler drain valve to a location where hot water can be safely discharged.

Drain approximately five gallons of water from the boiler and mix-in an appropriate amount of an approved boil-out
compound. Remove safety valve and refill the boiler with prepared solution through funnel. Replace safety valve.

d)    Run a hose or temporary piping from the 1-1/2” skimmer tap on the upper rear section to a location where hot water

can be safely discharged.

e) Start the burner. Run boiler for several hours, boiling the water, without generating steam pressure. Open the water

feed valve sufficiently to allow a slight overflow of water through the skimmer tapping drain line. Continue boiling
until water coming out is clear.

f)

Turn off the burner. Drain hot water from boiler through boiler drain valve to a location where hot water can be
safely discharged.  Refill the boiler to normal water line level. If water in the gauge glass does not look clear, repeat
above boil-out procedure again until water clears out.

g) Reinstall safety valve and related piping.
h) Conduct pH and Alkalinity test of water in the system. The pH reading should be in 7 to 11 range.

24

NOTE

When substantial amount of make-up water is used due to lost condensate, or when make-up water is hard or corrosive,
water treatment is required. Contact qualified water treatment company for recommended water treatment compounds
and procedure.

CAUTION

ATTEMPTS TO USE BURNERS OR BURNER CONFIGURATIONS OTHER THAN THOSE SHOWN IN
TABLE 3 COULD RESULT IN RELIABILITY PROBLEMS, DAMAGE TO THE BOILER NOT COVERED
UNDER WARRANTY, PROPERTY DAMAGE, OR UNSAFE OPERATION.

Содержание KSZ065 KSZ075 KSZ100 KSZ090

Страница 1: ...535 8900 Fax 215 535 9736 www crownboiler com Manufacturer of Hydronic Heating Products P O Box 14818 3633 I Street Philadelphia PA 19134 WARNING Improper installation adjustment alteration service or...

Страница 2: ...d by natural draft into a lined masonry or metal chimney or Type L vent An adequate supply of air for combustion ventilation and dilution of flue gases must be available in the boiler room This boiler...

Страница 3: ...ented 1 There is sometimes an accelerated rate of soot buildup on the oil burner cad cell spinner etc 2 There is a potential for severe damage to the side of the structure in the event that the boiler...

Страница 4: ...used follow vent pipe manufacturer recommendations for minimum clearances 3 Do not install this boiler directly on a combustible surface Where it is desired to install the KSZ over a non carpeted comb...

Страница 5: ...Openings Aligned To Permit Free Air Circulation 4 MIN Combustible Surface FIGURE 3 INSTALLATION OVER A COMBUSTIBLE FLOOR 4 6 6 18 6 24 LH SIDE CLEARANCE 24 FOR FLOAT TYPE LWCO EQUIPPED BOILERS CLEARAN...

Страница 6: ...ing and the bottom edge of the lower opening must be within 12 of the floor Figure 4 Each opening must have a free area of 1 square inch per 1000 BTU hr input of all fuel burning appliances in the boi...

Страница 7: ...7 FIGURE 4 BOILER INSTALLED IN CONFINED SPACE ALL AIR FROM INSIDE 6 FIGURE 5 ALL AIR FROM OUTDOORS VENTILATED CRAWL SPACE AND ATTIC...

Страница 8: ...8 7 FIGURE 6 ALL AIR FROM OUTDOORS VIA VENTILATED ATTIC FIGURE 7 ALL AIR FROM OUTDOORS USING OPENINGS INTO BOILER ROOM...

Страница 9: ...9 FIGURE 8 ALL AIR FROM OUTDOORS USING HORIZONTAL DUCTS INTO BOILER ROOM 8...

Страница 10: ...and Solid Fuel Burning Appliances NFPA 211 and lined with a clay liner or other listed lining system Do not vent a KSZ series boiler into an unlined chimney 2 Acceptable Vent Connectors The following...

Страница 11: ...nd the boiler collar as well as the barometric draft regulator Use at least three screws at each joint TABLE 2 MINIMUM RECOMMENDED BREECHING AND CHIMNEY SIZE Power Side Wall Venting Important Note Two...

Страница 12: ...is to separate tiny water droplets from the steam exiting the boiler so that dry steam is sent to the system If the near boiler piping is not correct wet steam will enter the system and the following...

Страница 13: ...lve spindle must be in vertical position into the 3 4 tapping on top of the boiler 3 Pipe the discharge of the safety relief valve to a location where water or steam will not create a hazard or cause...

Страница 14: ...ween the boiler and the circulator inlet All piping between the boiler and the circulator inlet should be 1 regardless of the size of the piping required in the rest of the system See Figure 17 in Par...

Страница 15: ...ackflushed to remove sediment WARNING A mixing valve does not eliminate the risk of scalding Set the mixing valve and boiler low limit adjustments as low as possible Feel water before showering or bat...

Страница 16: ...r system if needed 6 Unions Required Tankless heaters may require periodic gasket replacement or other maintenance which requires removal of the heater from the boiler Install unions anywhere in the t...

Страница 17: ...See Figure 13 A vertical distance from top of the tank to center line of the pump Dimension H over 8 feet will result in a pump inlet pressure in excess of the 3 psi limit in NFPA 31 b ONE PIPE LIFT...

Страница 18: ...ed to a one pipe gravity system as doing so will result in lower inlet line flow and longer filter life d TWO PIPE LIFT SYSTEM used when a fuel oil storage tank is located below an oil burner fuel pum...

Страница 19: ...l it as shown in the pump manufacturers s instructions Do not install this bypass plug on one pipe systems as pump seal damage will result 5 Do not use check valves especially on gravity feed systems...

Страница 20: ...cuit between thermostat and boiler Connect thermostat wire leads to terminals T and T on the burner primary control 3 Optional Tankless Heater Wiring Install the L4006Awith the 3 4 NPT well in the 3 4...

Страница 21: ...he CG450 2 Using McDonnell Miller WF2 U 120 feeder Do not alter factory boiler wiring Connect WF2 U 120 to CG450A as follows Connect terminal 1 on the feeder to terminal A on the CG450 Connect termina...

Страница 22: ...22 FIGURE 18a WIRING MCDONNELL MILLER 101A 120 OR HYDROLEVEL VXT 120 FEEDER TO BOILER EQUIPPED WITH 67 L W C O FIGURE 18b WIRING MCDONNELL MILLER WF2 U 120 FEEDER 21...

Страница 23: ...BURNERS CONSULT BURNER INSTRUCTION MANUAL FOR OTHER BURNERS CAD CELL 24 VOLT THERMOSTAT L4006A LIMIT CONTROL TANKLESS EQUIPPED BOILERS ONLY L1 INTERRUPTED INTERMITTENT BURNER MOTOR LIMIT VALVE L2 NOT...

Страница 24: ...steam systems the cut in pressure should be set at 0 5 psi with a 1 psi differential 12 Turn the line service switch to ON position 13 Crack open vent fitting on the oil pump and allow burner to run...

Страница 25: ...til about one inch of water is visible in gauge glass c Run a hose or temporary piping from the boiler drain valve to a location where hot water can be safely discharged Drain approximately five gallo...

Страница 26: ...SETTING 0 0 1 0 1 2 0 3 3 DRAFT OVER FIRE in w c MAX SMOKE bacharach scale FLUE CO2 MIN 11 0 11 0 11 0 11 0 11 0 11 0 11 0 11 0 11 0 MAX 12 5 12 5 12 5 12 5 12 5 12 5 12 5 12 5 12 5 PREPURGE IGNITION...

Страница 27: ...Hydrolevel CG450 manual for any additional maintenance information Test the low water cut off before placing the boiler back into service For McDonnell Miller 67 low water cut offs Remove and inspect...

Страница 28: ...ng order Vents should not permit any passage of steam or water Check all steam and return piping for leaks Be aware that buried return piping can leak and go undetected during normal operation 3 Allow...

Страница 29: ...e any accumulations of dust hair etc from the air shutter blower wheel and other air handling parts of the burner 5 Replace the fuel oil line filter element and gaskets 6 Inspect all oil piping and fi...

Страница 30: ...a 1ea 1ea 1ea 1ea 1ea 1ea 1ea 1ea 11 REFRACTORYBLANKET 1ea 275003 275003 275003 275004 275004 275004 275005 275005 275005 12 SWINGDOOR 270020 1ea 1ea 1ea 1ea 1ea 1ea 1ea 1ea 1ea 20 1 2 x1 SEALINGSTRIP...

Страница 31: ...31 30...

Страница 32: ...2 ea 2 ea 2 ea 2 ea 2 ea 2 ea 2 ea 2 ea 2 ea 54 TWIST RECEPTICAL 96 010 1 ea 1 ea 1 ea 1 ea 1 ea 1 ea 1 ea 1 ea 1 ea 55 TWIST RECEPTICAL COVER 96 019 1 ea 1 ea 1 ea 1 ea 1 ea 1 ea 1 ea 1 ea 1 ea 56 PR...

Страница 33: ...33 32...

Страница 34: ...34 Tel 215 535 8900 Fax 215 535 9736 www crownboiler com Manufacturer of Hydronic Heating Products P O Box 14818 3633 I Street Philadelphia PA 19134 CROWN Boiler Co Rev 2 05 03...

Отзывы: