5.5 VALVE ASSEMBLY

Assemble all components in reverse order to 5.3.

Lubricate generously with suitable ‘Anti Seize’ compound 
covering all threaded diameters in both body and seat. 
For standard designs: Ensure that the ‘Anti Seize’ 
compound is applied around the O-ring in the seat, and 
on the mating body diameter.
For alternative seat designs: Ensure that none of the ‘Anti 
Seize’ compound is applied around the seal area or on the 
seal itself. The sealing compound can affect the sealing 
capability at extreme temperatures.

When replacing the guide housing ensure an adequate 
amount of Furminite (or other suitable locking 
compound/thread seal) is applied to help lock the guide 
housing in place.
After assembly of valve, the valve should be 
hydrostatically tested by pressurising the valve on the 
downstream side and checking for leakage on the 
upstream side.

Note:

1.  Locktite 222 to be used to secure all screws.
2.  Item 11 Back up ring is only required for standard 

design valves, PN100 and above. (See figure 1)

5.5.1 PROXIMITY SWITCH ASSEMBLY (WHERE 
APPLICABLE)

(g)    Switch housing assembly (See Figure 3B)

1.  The threads in the body (1) for the switch housing 

(20) and the threads on the switch housing (20) 
should be cleaned thoroughly with petroleum 
solvent, or other suitable detergent.

2.  An even coating of “Jet-Lube” (Thick or Thin) thread 

paste is applied to the switch housing (20) threads.

3.  Screw the switch housing (20) into the body (1) and 

wrench tighten. (Care must be taken not to start 
screwing the switch housing in on the incorrect 
thread as this will damage the threads)

4.  The limit switch (21) is inserted fully into the switch 

housing, and followed by the switch spacer (27).

5.  The cable of the limit switch (21) should be passed 

through the cable gland (22) and the cable gland 
screwed into the switch housing (20).

(b)    Magnet housing assembly (See Figure 4)

1.  The 2 magnets (24) are joined together, opposite 

pole to opposite pole and inserted into the magnet 
housing (25) (the switch’s sensor detects the 

presence of a magnetic field, there is no preference 
in the polarity of the field, therefore the magnet can 
be inserted into the housing either pole first). Ensure 
the magnets (24) are positioned in the centre of the 
magnet housing (25) and secured in place with an 
anti-vibration sealant (or silicone), such as Belzona 
2221 Anti-Shock Compound.

2.  The magnet spacer (23) is placed in the magnet 

housing (25) on top of the magnets (24) so the holes 
in the spacer and housing are aligned.

3.  Insert the magnet housing assembly into the hole in 

the disc (3) so the hole in the magnet housing (25) 
and the hole in the disc line up. Secure in place with 
an anti-vibration sealant (or silicone).

4.  An even coating of “Jet-Lube” (Thick or Thin) thread 

paste is applied to the grub screw (26), which is 
screwed into the hole in the back of the disc (3) and 
tightened to secure the magnet housing (25) into the 
disc (3).
A small portion of the magnet housing (25) will 
protrude from the hole when fully inserted. This 
portion should not impede the axial motion of the 
disc (3) by colliding with the switch housing (20).

5.6 PROXIMITY SWITCH DISASSEMBLY

The disassembly of the Proximity Switch can be 
accomplished by simply reversing the assembly 
instructions in 5.5.1.

ALL THREADS MUST BE CORRECTLY TIGHTENED AND 
LOCKED.
DO NOT USE EXCESSIVE FORCE AT ANY POINT DURING 
ASSEMBLY.
IF IN DOUBT DIS-ASSEMBLE AND CHECK BEFORE RE-
ASSEMBLY.
REMEMBER: PLEASE USE EYE PROTECTION.

   CAUTION

!

Содержание NOZ-CHEK Cryogenic

Страница 1: ...www cranecpe com OPERATION AND MAINTENANCE INSTRUCTIONS NOZ CHEK Cryogenic Valves brands you trust Crane ChemPharma Energy ...

Страница 2: ...een low pressure loss and quick dynamic response keeping the reverse velocity to a minimum Further development and testing of the valve including updating to state of the art machining techniques and refined material selection means the Noz Chek now fully complies with BS 6364 cryogenic leak rates 1 2 CRYO NOZ CHEK FEATURES Cryogenic Service The Cryo Noz Chek valve is capable of achieving reduced ...

Страница 3: ...oss and wear of components This phenomenon is not exclusive to Crane equipment and should be applied to any pipe layout as good practice The pressure loss of any piece of piping equipment in a system will be affected by the presence of other equipment Pressure loss is an unrecoverable energy loss and is the measured decrease in pressure Measuring the pressure drop immediately before and after pipi...

Страница 4: ...ed by increased velocity in the minimal flow area results in additional force to assist the Disc to open and allows for extra spring loading that facilitates a faster closing time This spring force is balanced in the fully open position of the disc for a given velocity of flow This velocity depends upon the flow imposed by the service conditions and the Specific Gravity of the fluid The Noz Chek I...

Страница 5: ...oved for inspection See Figure 3A 5 3 VALVE DIS ASSEMBLY TYPICAL SEE FIGURE 1 Ensure that area upstream of seat 2 is clean and free from scale Valve should be resting on downstream side ensuring no damage to sealing face Valve may need to be secured to avoid rotation when dis assembling a Remove seat screw 13 and insert the Seat Extractor tool into the slots in the seat to unscrew the Seat 2 count...

Страница 6: ...limit switch 21 is inserted fully into the switch housing and followed by the switch spacer 27 5 The cable of the limit switch 21 should be passed through the cable gland 22 and the cable gland screwed into the switch housing 20 b Magnet housing assembly See Figure 4 1 The 2 magnets 24 are joined together opposite pole to opposite pole and inserted into the magnet housing 25 the switch s sensor de...

Страница 7: ... chek valves for use in Cryogenic Service Doc No ESB 3268 Revision 0 Checked P Burns Revision Date 25 08 20 Page 11 of 16 Crane Stockham Valve Ltd Registered Number L549383 Eng 6 Alexander Road Registered Address 100 Barbirolli Square Cregagh Belfast BT6 9HJ Manchester M2 3AB Phone 44 0 28 90 704222 Fax 44 0 28 90 401582 STOCKHAM VALVE Duo Chek Noz Chek Marlin Flowseal Center Line Item Quantity De...

Страница 8: ...ckham Noz chek valves for use in Cryogenic Service Revision 0 Checked P Burns Revision Date 25 08 20 Page 12 of 16 Crane Stockham Valve Ltd Registered Number L549383 Eng 6 Alexander Road Registered Address 100 Barbirolli Square Cregagh Belfast BT6 9HJ Manchester M2 3AB Phone 44 0 28 90 704222 Fax 44 0 28 90 401582 FIGURE 2 FIGURE 2 ...

Страница 9: ...ription 1 1 BODY 20 1 SWITCH HOUSING 21 1 SWITCH 22 1 GLAND 27 1 SWITCH SPACER FIGURE 3A FIGURE 3B Item Quantity Description 1 1 BODY 20 1 SWITCH HOUSING 21 1 SWITCH 22 1 GLAND 27 1 SWITCH SPACER CRANE Engineered Valve Division Subject Installation Operating and Maintenance manual for Crane Stockham Noz chek valves for use in Cryogenic Service Doc No ESB 3268 Revision 0 Checked P Burns Revision Da...

Страница 10: ... 16 Crane Stockham Valve Ltd Registered Number L549383 Eng 6 Alexander Road Registered Address 100 Barbirolli Square Cregagh Belfast BT6 9HJ Manchester M2 3AB Phone 44 0 28 90 704222 Fax 44 0 28 90 401582 STOCKHAM VALVE Duo Chek Noz Chek Marlin Flowseal Center Line Item Quantity Description 3 1 VALVE DISC 23 1 MAGNET SPACER 24 2 MAGNETS 25 1 MAGNET HOUSING 26 1 GRUB SCREW FIGURE 4 FIGURE 4 Item Qu...

Страница 11: ...oblem 6 3 The valve leaks excessively across seal a The seal is defective b Disc is not seating properly c The Spring Energised seal or Metal C Seal may be damaged d If the valve is fitted with a switch the grub screw may have become loose and the magnet housing is impeding the disc s movement To remedy this clean both threads thoroughly apply an even coat of Jet Lube Thick or Thin thread paste to...

Страница 12: ...Z CHEK PACIFIC VALVES RESISTOFLEX REVO SAUNDERS STOCKHAM TRIANGLE UNI CHEK WTA and XOMOX are registered trademarks of Crane Co All rights reserved brands you trust CPE NOZ CHEK CRYOGENIC IM EN A4 2020_08_26 Crane Energy Global Headquarters 4526 Research Forest Drive Suite 400 The Woodlands Texas 77381 U S A Tel 1 936 271 6500 Fax 1 936 271 6510 Crane Stockham Valve Ltd 6 Alexander Road Cregagh Bel...