CPG Freno Скачать руководство пользователя страница 6

5

INST

ALLA

TION MANUAL

Construction Scheduling Considerations

Schedule installation and fill of the Freno™ System at a time when surrounding 

surfaces have been stabilized and sedimentation is controlled.  It is critical that the 

bio-retention fill not become contaminated by sedimentation during construction. 

A typical Freno™ installation will be completed rapidly (one to two days of 

construction time per structure is typical, depending on complexity and size), but 

some care should be taken if construction will be interrupted for any reason, or if the 

surrounding site soils are not stabilized.

The planting soils should not be delivered to the site before the Freno™ System has 

been installed and the under-drain system, if any, has been installed.

It may be most efficient to place the plant materials after paving has been 

completed to avoid repetition of effort since performing the paving work may 

require access from within the bio-retention area, which could damage the plant 

materials.

The construction sequence is very straightforward:

Stage

Material

Typical Equipment 

Required

1

Pre-Construction Site 

Review

Safety barriers and markers

None

2

Site Preparation, 

Demolition and 

Excavation (installation of 

under-drain, if required)

Under-drain system materials (if 

required). Order base material 

and Freno Module delivery.

Compact excavator and 

skid-steer loader

3

Place and Compact Base 

Leveling Pad

Base Material and Freno Mod-

ules

Plate compactor,  

skid-steer loader

4

Place Freno Modules

Pins, Lifting Clutches

Compact excavator or 

skid-steer loader

5

Backfilling and  

Planting

Crushed stone backfill, Bio-

retention fills - planting soils, 

sands and aggregates, plants

Skid-steer loader

SCHEDULING

Содержание Freno

Страница 1: ...A INSTALLATION MANUAL INSTALLATION MANUAL Modular Rain Garden...

Страница 2: ...required to install the system one machine operator and one laborer Each Freno module has built in connection inserts that allow easy attachment to lifting equipment using 3 4 common thread bolts The...

Страница 3: ...ions of structures The modules each have lifting connections placed to assist in connecting the system to lifting equipment to facilitate placement of the modules during construction and for potential...

Страница 4: ...Endless Options The Freno System allows great flexibility in the construction of a variety of structure configurations because it is a kit of parts Here are several examples of possible configuration...

Страница 5: ...the site while under construction and divert traffic dangers away from site workers Pre Construction Site Review Obtain engineering plans for the project and any required permits Note any access rest...

Страница 6: ...It may be most efficient to place the plant materials after paving has been completed to avoid repetition of effort since performing the paving work may require access from within the bio retention ar...

Страница 7: ...rench as much as possible recommendation regarding amount of over excavation and illustration Rendering of plan view of recommended trench configuration If your system will include an under drain exca...

Страница 8: ...a level condition to the elevation specified in the plans The leveling pad should be 18 wide and at least 6 thick after compaction see drawing for typical leveling pad dimensions and placement which...

Страница 9: ...pact Excavator capable of lifting _____ lbs Attach the lifting attachments to the Freno Module using the lifting connections Figure ___ that allow connection to bolts with 3 4 common thread Connect th...

Страница 10: ...een backfilled but will help assure the modules stay in their proper position during construction To assist in leveling the module a heavy plastic covered mallet may be useful to seat the module and m...

Страница 11: ...2 Establish a corner by placing next module Using a second T2 panel install the foundation for the intake structure Confirm this module is level at the right elevation and oriented correctly before m...

Страница 12: ...t alignment and elevation as you go Step 4 Once the first side is completed start installing the modules on the other side Step 5 Continue installing Modules on this side Place a connecting rod in the...

Страница 13: ...Module to provide proper spacing for placement of the last Side Module Step 7 Install the final side Module Step 8 Install the water intake structures using the N Mod ules as shown in Stage 3 D Here...

Страница 14: ...Stage 4 below backfill the exterior of the structure near and around the intake structure with angular crushed stone being careful to assure that the T 2 modules remain correctly aligned and level Pl...

Страница 15: ...he system are backfilled in alternating lifts Remove temporary shoring Follow the plan specifications for material types and layer thicknesses of the bio retention fill materials Do not compact the in...

Страница 16: ...should not be placed in service until all of the drainage area has been stabilized and approved by the inspector If there will be any delays before paving is completed make sure sediment controls rema...

Страница 17: ...leaders in the concrete products industry We offer high performance cost effective products for the construction of buildings stormwater management and low impact development of sites 800 789 0872 ww...

Отзывы: