Version 1.0b
4
INSTALLATION, GENERAL
Installation of the IN-6200 blower system is relatively simple, if a homeowner has planned for the
installation of the optional blower system during Inglenook installation. This means that a qualified
electrician should have already made all the necessary electrical connections between the home’s electrical
system and the Inglenook fireplace. The only thing left to do to install the IN-6200 is:
a)
install the dual blowers and electrical motor that is magnetically held in place,
b)
install the thermo disk provided with the kit that will be used to control the on/off cycles of
the blower system,
c)
install and make final connections to the wiring harness which have been greatly simplified
by the design of the wiring harness,
d)
finally, the last step is to plug the blower system into a properly grounded U.L. approved
duplex outlet that was provided for during the manufacturing of the Inglenook fireplace
system and should already be connected to the home’s electrical system.
INSTALLATION, ELECTRICAL
Installation of the IN-6200 blower system should take less than 30 minutes if a qualified electrician has
previously connected the Inglenook fireplace to the home’s electrical system. The Inglenook fireplace and
the Inglenook blower system must be electrically connected and grounded in accordance with local codes,
or in the absence of local codes, with the current NFPA 70 National Electric Code or in Canada, with CSA
C22.1 Canadian Electrical Code.
FIGURE 1 is a detailed drawing of the Inglenook electrical system installed in a typical home. A qualified
electrician should make all the necessary electrical connections during installation of the Inglenook
fireplace. Note that the IN-6200 blower speed control (rheostat) can be located on any wall that suits the
homeowner. Country Flame provides an electrical box for the rheostat; however, this part will not be
required if the electrician has already completed the wiring of the Inglenook as there should already be an
electrical box ready for the rheostat to be installed in. If all electrical connections to the fireplace are
complete, then installing the IN-6200 blower system is a “plug-n-operate” process.
INSTALLATION, PREPARATION
Unpack the IN-6200 kit and ensure that all parts have been included in the kit. Ensure that no shipping
damage has occurred. If shipping damage has occurred, notify the shipping agency immediately and notify
the local Country Flame Dealer where this product was purchased. The following items should be included
in the IN-6200 kit:
-
Blower motor with double squirrel cage blades and partial wiring harness
-
3 prong power cord (do not remove grounding pin), ready for connection to blower harness
- 110
0
F heat sensor
-
Rheostat, blower speed control
-
Rheostat control knob
-
Rheostat electrical box
-
Warning Label, (1) Caution, Electrical Hazard & (1) Warning, Inglenook Blower Only
-
Screws, (2) 12-24 by 3/8” Type F
-
Screws (2) 10-32 by 3/8” PMS
-
Screw (1) #6 by 3/8” PMS ground connection
-
Owner’s Manual; IN-6200 IOM Manual
The only tool that should be required for installation is a screwdriver or nut socket used to install the thermo
snap disk to the thermo snap disk mount and mount the rheostat.