Store the fan in a dry, weather-protected place and cover with a tarpaulin to protect it from dust and
soiling.
If stored for over one year, test whether the fan bearings rotate freely before putting into operation.
4
Installation, configuration
Before installation, check whether all the locking screws (including the motor
screws) are tightened properly.
Check the electrical connections if wired at the factory
.
Before installation, check that there are no foreign bodies in the coil or in the
intake and pressure connections.
The fan must be installed at a location provided and prepared by the customer and must be secured and
connected in such a way that any possible vibration occurring can be absorbed by the vibration dampers
supplied by COLASIT.
If no ducting is foreseen on the intake side, the intake connection should be protected by a sturdy protective
grating (10mm mesh) to be provided by the customer.
Connection ducting on the pressure side must be routed to prevent the backflow of foreign bodies, rainwater
or condensate into the fan. To ensure this, please use the COLASIT condensate drain nozzles.
Due to the possibility of noise nuisance, we recommend that the fan should not be installed in the
immediate vicinity of workplaces.
5
Commissioning, initial startup, test run
The fan should only be put into operation after inspection and approval by the
safety officer.
5.1
Inspection of the installation and settings
Check list:
Prior to commissioning and initial start-up, it must be guaranteed that
the fan is installed vibration-free and mechanically secured,
all components are cleaned both on the inside and the outside and are free from foreign bodies,
all intake and pressure ducts connections are leak-proofed
all rotating parts are protected against unintentional contact,
the electrical connections are installed and their function tested,
a lockable main control switch is available to which the fan is connected
the EMERGENCY-STOP equipment is functionally tested,
the safety inspector has made sure that safety equipment exists,
the operating personnel is familiar with the operating manual,
the safety inspector has given his approval fort he operation of the installation and that no external
persons are present in the plant area
If envisaged by procedural regulations provided by the operator, minutes have to be taken on the
commissioning work, including the observance of the check list.