Operation
The screen displays the operational status of the machine throughout the cycle.
1. Machine is filling.
2. Wait light is illuminated.
3. Progress bar shows fill time
remaining.
1. When power switch is turned ON,
system information screen will
show briefly.
2. This shows firmware version,
parameter settings, and cycle
counts.
1. Red thermometer indicator
shows booster tank is heating.
2. Wait light remains illuminated.
3 Wait light indicates cycle is
pending.
4. Progress bar shows remaining
heat time.
1. Booster heater has achieved
temperature
2. Blue thermometer bar shows the
wash tank heat is active.
3. Wait light is out and READY
shows a cycle may begin.
1. Ready indicates the machine will
wash.
2. 155 °F indicates the wash tank
temperture.