  Installation of a factory supplied liquid line 

bi-directional filter drier is required. Never install a suction 

line filter in the liquid line.

� 

CAUTION! 

See compressor section IOM for refrigerant charge 

information.

Line Set Installation

Figure 7 illustrates a typical installations of an air handler or 

cased coil matched to an indoor compressor section. Table 

2 shows typical line-set diameters at various lengths. Lineset 

lengths should be kept to a minimum and should always be 

installed with care to avoid kinking. Line sets are limited to 60 

feet (18 meters) in length (one way). Line sets over 60 feet void 

the equipment warranty. If the line set is kinked or distorted, and 

it cannot be formed back into its original shape, the damaged 

portion of the line should be replaced. A restricted line set will 

effect the performance of the system. 

All brazing should be performed using nitrogen circulating 

at 2-3 psi [13.8-20.7 kPa] to prevent oxidation inside the 

tubing. All linesets should be insulated with a minimum 

of 1/2” [13mm] thick closed cell insulation. All insulation 

tubing should be sealed using a UV resistant paint or 

covering to prevent deterioration from sunlight.

When passing refrigerant lines through a wall, seal 

opening with silicon-based caulk. Avoid direct contact 

with water pipes, duct work, floor joists, wall studs, 

floors or other structural components that could transmit 

compressor vibration. Do not suspend refrigerant tubing 

from joists with rigid straps. Do not attach line set to the 

wall. When necessary, use hanger straps with isolation 

sleeves to minimize transmission of line set vibration to 

the structure.

Installation

Figure 5: Air Coil Connection

Sensing Bulb

IMPORTANT: 

DO NOT perform any brazing with the TXV 

bulb attached to any line. After brazing operations have been 

completed, clamp the TXV bulb securely on the suction line 

at the 10 or 2 o’clock position with the strap provided in the 

parts bag. Insulate the TXV sensing bulb and suction line 

with the provided pressure sensitive insulation.

IMPORTANT:

 TXV sensing bulb should be located on a 

horizontal section of copper suction line, just outside of 

coil box. The copper sensing bulb must never be placed 

on any aluminum tube as this will result in galvanic 

corrosion and eventual failure of the aluminum tube.

IMPORTANT:

 Always protect TXV from heat when brazing.

Air Coil

To obtain maximum performance of a newly manufactured 

air coil it should be cleaned before start-up. A 10% solution 

of dishwasher detergent and water is recommended for both 

sides of the coil. A thorough water rinse should follow.

CAUTION!

  HFC-410A systems operate at higher 

pressures than R-22 systems. Be certain that service 

equipment (gauges, tools, etc.) is rated for HFC-410A. 

Some R-22 service equipment may not be acceptable.

TXV w/Internal Check Valve 

Suction Line

Liquid Line

Bulb 

(Must be

Installed and

Insulated)

Equalizer

Line

LT2

Sensor

Installing the Indoor Coil and Lineset

Figure 5 shows the installation of the lineset and TXV bulb 

to a typical indoor coil. Braze the copper line set to the coil. 

Nitrogen should be circulated through the system at 2-3 psi 

[13.8-20.7 kPa] to prevent oxidation inside the refrigerant 

tubing. Use a low silver phos-copper braze alloy on all brazed 

connections.

Model

20 feet [6 meters]

40 feet [12 meters]

60 feet [18 meters]

Liquid 

Suction

Liquid

Suction

Liquid

Suction

TES/P026 in. 

3/8

"

 

3/4

"

 

3/8" 

3/4

"

 

3/8"

3/4

"

 

TES/P038 in. 

3/8

"

 

7/8

"

 

3/8

"

 

7/8

"

 

3/8

"

 

7/8

"

 

TES/P049 in. 

3/8

"

 

7/8

"

 

3/8

"

 

7/8

"

 

3/8

"

 

7/8

"

 

TES/P064 in. 

1/2

"

 

7/8

"

 

1/2

"

 

7/8

"

 

1/2

"

 

7/8

"

* 60 feet (18 meters) is the maximum line set length.

Table 2: Line Set Diameters

Содержание TAH 026-A

Страница 1: ...Table of Contents Model Nomenclature 3 General Information 4 Pre Installation 4 Safety 5 Physical Data 6 Dimensional Data 7 Installation 8 13 Installation AXM Control 14 Electrical Thermostat Wiring...

Страница 2: ...Tranquility Digital Air Handler TAH R ev Au gu st 21 2018 2 Geothermal Heating and Cooling This page was intentionally left blank...

Страница 3: ...DLER CONFIGURATION 026 NOMINAL CAPACITY 038 049 REVISION 064 CABINET SIZE S 12 FUTURE USE SIZE 026 ONLY 18 5 WIDTH SIZES 026 038 049 ONLY 22 5 WIDTH SIZES 038 049 064 25 5 WIDTH C 7 C CURRENT REVISION...

Страница 4: ...the claim without recourse Note It is the responsibility of the purchaser to file all necessary claims with the carrier Notify your equipment supplier of all damage within fifteen 15 days of shipment...

Страница 5: ...avoided will result in death or serious injury DANGER labels on unit access panels must be observed WARNING Indicates a potentially hazardous situation which if not avoided could result in death or se...

Страница 6: ...e Fan Motor hp 1 2 1 Blower Wheel Size Dia x W in mm 9 x 7 229 x 178 11 x 10 279 x 254 Air Coil Dimensions H x W in mm 14 x 17 356 x 432 24 x 17 610 x 432 24x17 610 x 432 Filter Standard 1 25mm Thick...

Страница 7: ...l and Downflow Configuration C Secondary Drain Horizontal Configuration A B C Cabinet Size Overall Cabinet Supply Air Opening Return Air Opening F G H J A Width B Height C Depth D Width E Depth DD Wid...

Страница 8: ...aled Location of power entry is shown on the outline drawing 5 After ductwork connections are made seal airtight and per local codes 6 The unit is then placed with the blower side down and the coil is...

Страница 9: ...ust be placed under the unit 4 It is always recommended that an auxiliary drain pan be installed under a horizontal air handler See figure 2 to prevent possible damage to ceilings 5 Isolate the auxili...

Страница 10: ...urn Discharge Discharge TOP DISCHARGE Return Return Discharge Discharge Figure 4 Air Handler Orientation TAH 1 to 2 Filter Rack Conversion The unit is shipped with1 filter rack from the factory The co...

Страница 11: ...n Figure 5 Air Coil Connection Sensing Bulb IMPORTANT DO NOT perform any brazing with the TXV bulb attached to any line After brazing operations have been completed clamp the TXV bulb securely on the...

Страница 12: ...cleaning of the primary drain line should it become necessary Install condensate trap at each unit with the top of the trap positioned below the unit condensate drain connection as shown in Figure 6 D...

Страница 13: ...H Rev Augus t 2 1 2 0 1 8 climatemaster com Installation Figure 7 Typical Split Air Handler Installation Compressor Section Low Voltage Insulated Linesets Air Pad or Extruded Polystryene PVC Condensat...

Страница 14: ...igure 5 and connected to the AXM control No additional action required do not clip the VIO wires Installation Test Button The test button puts the AXM into test mode which bypasses the soft start ramp...

Страница 15: ...Non Communicating thermostat and AXM communicating control in Tranquility Digital Air Handler Figure 11 Connection to Non Communicating thermostat AXM control and Tranquility TTS Non Communicating Sp...

Страница 16: ...2 O Dehumid First Stage Heating Y1 Second Stage Heating Y1 Y2 Third Stage Auxiliary Heating Y1 Y2 W Emergency Heating W with no Y1 or Y2 Fan G with no Y1 Y2 or W The ECM motor includes soft start and...

Страница 17: ...00 800 800 600 1000 850 1000 1000 Minimum 600 450 550 400 600 450 300 700 TAH 038 0 9 1 2 Default 1050 800 850 650 1100 850 550 1350 Maximum 1500 1100 1200 900 1500 1100 1500 1500 Minimum 900 600 825...

Страница 18: ...range wire from power block T2 and insulate open end of wire Connect the white lead from transformer primary wire to power block terminal T2 Note L2 will be used as Netural 3 Remove plug in ECM power...

Страница 19: ...19 Tranquility Digital Air Handler TAH Rev Augus t 2 1 2 0 1 8 climatemaster com Typical Wiring Diagram 96B0005N55...

Страница 20: ...aned to obtain maximum performance Check once a year under normal operating conditions and if dirty brush or vacuum clean Care must be taken not to damage the aluminum fins while cleaning CAUTION Fin...

Страница 21: ...labels or rating labels have been removed or defaced 5 Products on which payment to CM or to the owner s seller or installing contractor is in default 6 Products which have not been installed and main...

Страница 22: ...Tranquility Digital Air Handler TAH R ev Au gu st 21 2018 22 Geothermal Heating and Cooling Notes...

Страница 23: ...23 Tranquility Digital Air Handler TAH Rev Augus t 2 1 2 0 1 8 climatemaster com Notes...

Страница 24: ...ntained herein are not express warranties and do not form the basis of any bargain between the parties but are merely ClimateMaster s opinion or commendation of its products Engineered and manufacture...

Отзывы: