manualshive.com logo in svg
background image

1943052    

V1.3   

June 2019 

 

 

 
 

 

 

 

 

 

Clevertest and Clevertest Plus 

 

Refer to the supplementary operation guide supplied with the Product. 
 

After Power ON, the Status LED on a Clevertest Plus enabled fitting will display a rapid Green or 
Red flashing for a period up to 2 minutes. 

 

Zoneworks and DATA Monitored Options

 

Ultrablades  with  part  numbers  -ZW

,  -DATA 

are  fitted  with  Zoneworks  communications  modules 

(nodes).  These  fittings  are  monitored  using  either  Powerline  Carrier  Technology  that  utilises  the 
power cable to provide data communication or a dedicated data cable to/from data routers installed 
on  a  dedicated  data  trunk  connected  to  a  central  Server  (can  also  be  connected  via 
Ethernet/Internet/Fibre). Zoneworks software on the server is used to monitor, coordinate testing and 
collate test data from each Ultrablade and can be commissioned by a single push of the test switch, 
or scanning of the supplied barcode. The LED Test Switch indicator provides a multifunction indication 
of the status of the Ultrablade during testing and normal operation: 

State

 

LED Operation

 

Commissioned 

LED on Solid (Green) 

Un-commissioned 

LED flashes at 0.5Hz (0.5s Green, 0.5s Yellow) 

Emergency Light Test In Progress 

LED flashes at 3s On (Yellow) & 0.5s Off 

 
In the case of the DATA version a 2-

way “figure 8” cable and terminal block facilitates the 

connection to the DATA network via a multi-drop bus (daisy chain connection).    For further 
information of installation of a Zoneworks LW system, please refer to the Zoneworks Users Guide 
and Commissioning Guide (incl. DATA version)   
 

DALI EM Option

 

Ultrablades with part numbers 

-DALI 

are fitted with DALI modules (nodes) that facilitate connection 

and  integration  to  3

rd

  Party  Lighting  Control  Systems.    Before  installing  the 

–DALI  fitting  please 

confirm that the Lighting Control System has the capability to monitor DALI Emergency Luminaires.   
The 

–DALI fitting will be addressed and configured into the control system by the Lighting Control 

System Commissioning Technicians and not Clevertronics.     

State

 

LED Operation

 

Commissioned/ Un-commissioned 

LED on Solid (Green) 

Emergency Light Test in progress 

LED flashes at 1s On (Yellow) & 1s Off 

“IDENTIFY COMMAND” 

Fitting goes into emergency mode for 10 seconds 

 
A 2-

way “figure 8” cable and terminal block facilitates the connection to the DALI network.    DALI 

connections are marked as Da Da.   
 

Networking: 

When installing the L10 Ultrablade PRO on a monitored network, (

ZONEWORKS, DATA, DALI

) simply 

insert the relevant Smart Node PCA.

 

 

 

 

 

Installation:

 

The L10 Ultrablade Pro Surface Mount LED Exit (LUBPRO-SM) is a surface mount fitting. The LUBPRO-
SM can be attached directly to any solid surface. Please follow the steps below to install the LUBPRO Exit: 

 

Open the fitting using the 2 screws on either side of the blade. 

 

Locate the mounting surface. 

 

Drill holes in the mounting base to suit the mounting method, Ceiling or Wall (see images below). 

 

Use the mounting bracket to mark-out the mounting holes for Ceiling or Wall Mount. 

 

Drill power access hole as required. 

 

Mount the fitting using appropriate fixings. 

 

Route the power to the mains connection and connect the 240VAC supply. 

 

Attach the blade assembly to the bracket and tighten the 2 mounting screws. 

 

Apply power to the fitting and test. 

 

If the CTP capabilities are activated, please affix the CTP Status Label to a visible surface.

 

Changing EXIT Legend Inserts

:

   

 

The Ultrablade Pro Exit comes with an assortment of standard legends.   
1. 

To remove the legend, grasp the centre of the bottom trim piece and pull down slightly to expose 
the legend edge. See photo. 

2. 

Grasp the bottom edge of the legend and slide the existing legend out of the blade, while working 
the edges out along the sides. 

3. 

Slide the new legend into the blade, ensuring to fit the edges into the sides then slide the legend to 
the top of the blade. Insert one bottom corner then the other. Slide the legend down into the 
bottom trim. 

 

 

 

 

Отзывы: