Installation: 

The Jumbo LED Exit can be Wall or Ceiling Mounted:  

Wall Mounting

 (single sided) 

 

Remove one of the corner trim pieces 

 

Remove the back mounting plate. 

 

Determine power entry  

 

Position the mounting plate in the mounting position.  

 

Mark the 4 holes for mounting. Then install the appropriate fixings (not supplied). 

 

Reinstall the mounting plate to the fitting. 

 

Install the fitting on the mounting hardware, while routing the power cable through the access hole. 

 

Ensure connection of the grounding strap between the fitting and the back plate. 

 

Connect the 240VAC supply to the terminal block. 

 
Ceiling Mounting

 (single or double sided) 

 

Remove one of the corner trim panels. 

 

Remove the diffuser panel. 

 

If converting to double-sided, remove the earth strap from the back plate before removing it. 

 

Determine power entry  

 

Position the fitting in the mounting position.  

 

Mark the mounting holes at the top of the fitting. 

 

Then install using the appropriate fixings (not supplied). 

 

Position the fitting while routing the power cable and attach to the surface as required. 

 

Connect the 240VAC supply to the terminal board. 
 

If the CTP capabilities are activated please affix the CTP status Label to a visible surface. 

 

Networking: 

When installing the product on a monitored network, (ZONEWORKS, DATA, DALI) simply insert the 
relevant Smart Node PCA. 
 

Images and Dimensions:

 

 

 

Wall Mounting Plate 

 

 

Ceiling Mounting Plate 

Clevertronics Clevertest and Clevertest Plus 

 

Refer to the supplementary operation guide supplied with the Product.

 

 

 

Zoneworks and DATA Monitored Options

 

Exits with part numbers LJELED*-ZW

,  LJELED*-DATA 

are fitted with Zoneworks  communications 

modules (nodes).These fittings are monitored using either Powerline Carrier Technology that utilising the 
power cable to provide data communication or a dedicated data cable to/from data routers installed on a 
dedicated data trunk connected to a central Server (can also be connected via Ethernet/Internet/Fibre). 
Zoneworks software on the server is used to monitor, coordinate testing and collate test data from each 
Exit. Zoneworks Exit can be commissioned by a single push of the test switch, or scanning of the supplied 
barcode. The LED Test Switch indicator provides a multifunction indication of the status of the fitting during 
testing and normal operation: 

State

 

LED Operation

 

Commissioned 

LED on Solid (Green) 

Un-commissioned 

LED flashes at 0.5Hz (0.5s Green, 0.5s Yellow) 

Emergency Light Test In Progress 

LED flashes at 3s On (Yellow) & 0.5s Off 

 
In the case of the DATA version a 2-way “figure 8” cable and terminal block facilitates the connection to 
the DATA network via a multi-drop bus (daisy chain connection).  For further information of installation of 
a Zoneworks system, please refer to the Zoneworks Users Guide and Commissioning Guide (incl. DATA 
version)  
 

DALI EM Option

 

Exits with part numbers L

JELED-DALI 

are fitted with DALI modules (nodes) that facilitate connection and 

integration to 3

rd

 Party Lighting Control Systems.  Before installing the LJELED*-DALI please confirm that 

the Lighting Control System has the capability to monitor DALI Emergency Luminaires.  The LJELED-
DALI will be addressed and configured into the control system by the Lighting Control System 
Commissioning Technicians and not Clevertronics.   

State

 

LED Operation

 

Commissioned/ Un-commissioned 

LED on Solid (Green) 

Emergency Light Test in progress 

LED flashes at 1s On (Yellow) & 1s Off 

“IDENTIFY COMMAND” 

Fitting goes into emergency mode for 10 seconds 

 
A 2-way “figure 8” cable and terminal block facilitates the connection to the DALI network.  DALI 
connections are marked as Da Da.  
 

Power Access 

Mounting Holes 

Power Access 

Mounting Holes 

 

 