Installation Guide /  PostMount 1-A for XL Panel

6

Code-Compliant Planning and Installation Guide V 1.1 - Complying with AS/NZS1170.2-2011 ADMT 4-2016

- Installation Instruction -

Installation Instruction

Dig a hole with the diameter of 300mm.

Place the pole into the middle of the hole and fillit with concrete. 
Maintain the position of the post. The allowed vertical tolerance is 
±2°.Keep the axle of the 2- Ø14 holes parallel to East-West;keep the 
vertical angle deviation within ±5°.For more than one system on one 
site maintain all the axles of 2- Ø14 holes aligned.

1) As show in figure on the right, with M12 * 120 hex bolts and nuts to 
lock Angle Steel 63*40*1250 on the Pole. And then use M12 * 120 hex 
bolts and nuts to lock supporting rod 40 * 40 * 682 on the Pole.

Note:
supporting rod around multiple holes which can be adjusted by 
adjusting the mounting,adjustable angle of 10 °, 20 °, 30 °, 40 °, 50 ° 
and 60 °.

Recommended torque for M12 bolts is 40~45 N·m

2) As show in figure on the right, place the ECO-Rail on Angle Steel. 
Use the Cross Connection Clamp, Cup head square neck bolts M8*25, 
Hexagon nut with flange M8 to lock on the Angle Steel 63 * 40 * 1010

Recommended torque for M8 bolts is 18~20 N·m

1. Pole 83*2400 Installation

2. PostMount 1-A Kit Installation

Содержание PV-ezRack PostMount 1-A

Страница 1: ...PostMount 1 A for XL Panel Code Compliant Planning and Installation Guide V 1 1 Complying with AS NZS1170 2 2011 ADMT 4 2016 Last Updated Mar 2022...

Страница 2: ...8 12 Clenergy PV ezRack PostMount 1 A for XL Panel up to 2100 x 1100 mm is a ground mounting system suitable for large scale commercial and utility scale installations PVezRack PostMount 1 A for XL Pa...

Страница 3: ...ng Marker Pen Spanner Anchoring Kit Torque Wrench Mixing Nozzles 5m Tape Components C U 30 46 G Universal Clampx4 ER AP PM1 A LP PostMount 1 A Kitx1 ER P 83 2400 Polex1 EZ GL ST Grounding Lugx2 ER SC...

Страница 4: ...w Side view drawing of PV ezRack PostMount 1 A for XL Panel is shown below The panels tilt angle and embedment depth below are for reference only Please refer to Certificate Letter to obatin the certi...

Страница 5: ...to reduce this risk Reduce the friction coefficient 1 Ensure that the thread surface is clean no dirt or contaminant 2 Apply lubricant grease or 40 engine oil to fasteners prior to tightening to avoid...

Страница 6: ...s All drawings and dimensions in this installation guide are for generic reference The PV ezRack PostMount 1 A for XL Panel is to be optimized to suit specific conditions for each project and document...

Страница 7: ...in all the axles of 2 14 holes aligned 1 As show in figure on the right with M12 120 hex bolts and nuts to lock Angle Steel 63 40 1250 on the Pole And then use M12 120 hex bolts and nuts to lock suppo...

Страница 8: ...fix the PV Panel to the Rails by using Universal Clamps Recommended torque for M8 bolts is 18 20 N m There are three solutions for Grounding Lug installation Solution 1 Fix the Grounding Lug at the en...

Страница 9: ...ation Guide and schematic drawings of the system components provided by Clenergy Australia Part number Description ER R ECO 2100 PV ezRack ECO Rail 2100mm ER RT 100 3400 PV ezRack PM4 Rectangular Tube...

Страница 10: ...ompliant Planning and Installation Guide V 1 1 Complying with AS NZS1170 2 2011 ADMT 4 2016 Certification REF CL 10129 S Internal REF 00142 Steel 300 MPa Aluminium 240 MPa Maximum tilt angle options r...

Страница 11: ...Installation Guide PostMount 1 A for XL Panel 10 Code Compliant Planning and Installation Guide V 1 1 Complying with AS NZS1170 2 2011 ADMT 4 2016 Certification REF CL 10129 S Internal REF 00142...

Страница 12: ...ft class soil 1 60 wet clays silty loams wet loose sands Notes 1 Terrain Category 2 TC2 refers to open terrain including grassland with well scattered obstructions having heights generally from 1 5m t...

Страница 13: ...assessment is always recommended and Clenergy must be informed on the outcome of the soil report Construction is to be carried out strictly on accordance with the instruction manual This work was des...

Страница 14: ...St Clayton VIC 2168 Australia Phone 61 3 9239 8088 Email sales clenergy com au Web www clenergy com au Clenergy Clenergy_global ClenergyClub Clenergy ClenergyGlobal ClenergyClub ClenergyAUS A Clenergy...