Chapter 4 Turn Up a Network
Before You Begin
NTP-H27 Provision a Point-to-Point Network
Step 1
Complete the
“DLP-H29 Log into CTC” task on page 16-43
at the ONS 15310-MA SDH on the network
where you want to provision a point-to-point configuration. If you are already logged in, continue with
Step 2.
Step 2
Click the
Provisioning > Protection
tabs. Verify that 1+1 protection is created for an optical port on the
15310E-CTX-K9. Complete the
“NTP-H142 Create Protection Groups for ONS 15310-MA SDH”
if protection has not been created.
Step 3
Repeat Steps
and
for the second point-to-point node.
Step 4
Verify that the working and protect ports in the protection groups correspond to the physical fiber
connections between the nodes, that is, verify that the working port in one node connects to the working
port in the other node and that the protect port in one node connects to the protect port in the other node.
Step 5
Complete the
“DLP-H52 Provision Section DCC Terminations” task on page 16-68
for the working
optical port signal on both point-to-point nodes. Alternatively, if additional bandwidth is needed for CTC
management, complete the
“DLP-H53 Provision Line DCC Terminations” task on page 16-71
Note
DCC terminations are not provisioned on the protect ports.
Note
If the point-to-point nodes are not connected to a LAN, you will need to create the DCC
terminations using a craft (direct) connection to the node. Remote provisioning is possible only
after all nodes in the network have DCC terminations provisioned to locked on the
15310E-CTX-K9 ports for the ONS 15310 MA.
Step 6
As needed, complete the
“DLP-H47 Provision a Proxy Tunnel” task on page 16-64
Step 7
As needed, complete the
“DLP-H48 Provision a Firewall Tunnel” task on page 16-65
.
Step 8
As needed, complete the
“DLP-H49 Create a Provisionable Patchcord” task on page 16-66
on both
point-to-point nodes.
Step 9
Complete the
“DLP-H50 Change the Service State for a Port” task on page 16-67
to put the protect port
locked.
Step 10
Verify that timing is set up at both point-to-point nodes. If not, complete the
Step 11
Complete the
“NTP-H28 Point-to-Point Network Acceptance Test” procedure on page 4-4
Stop. You have completed this procedure.
Purpose
This procedure provisions two ONS 15310-MA SDH nodes in a 1+1
point-to-point (terminal) network.
Tools/Equipment
None
Prerequisite Procedures
NTP-H26 Verify Node Turn-Up, page 4-2
Required/As Needed
As needed
Onsite/Remote
Onsite
Security Level
Superuser
Содержание ONS 15310-MA SDH
Страница 20: ...Figures xx Cisco ONS 15310 MA SDH Procedure Guide Release 9 1 and Release 9 2 78 19416 01 ...
Страница 45: ...xlv Cisco ONS 15310 MA SDH Procedure Guide Release 9 1 and Release 9 2 78 19416 01 Preface ...
Страница 48: ...xlviii Cisco ONS 15310 MA SDH Procedure Guide Release 9 1 and Release 9 2 78 19416 01 Preface ...
Страница 290: ...15 4 Cisco ONS 15310 MA SDH Procedure Guide Release 9 1 and Release 9 2 78 19416 01 Chapter 15 Power Down the Node ...