Installation Instructions
MSP-YM4 / MSP-YMACC1
5
INSTALLATION
Locate Mounting Site
WARNING:
IMPROPER INSTALLATION CAN LEAD TO
MOUNT FALLING CAUSING SEVERE PERSONAL INJURY
OR DAMAGE TO EQUIPMENT! It is the installers
responsibility to make certain the structure to which the
mount is being attached is capable of supporting five times
the combined weight of all components located between the
MSP-YM4 up to (and including) the displays [not to exceed
300 lbs (136.1 kg) for the MSP-YM4, and not to exceed
75 lbs (34.0 kg) for the MSP-YMACC1].
Preparing Rails
1.
Using the mount connector allen key (G), connect two rails
(B) by turning the rail connector (H) half way into one end of
the rail. (See Figure 1)
Figure 1
2.
Connect a second rail (B) to the first rail by connecting it to
the rail connector (H) extending from the end of the first rail.
(See Figure 2)
3.
Tighten until the rail connector (G) is no longer visible.
4.
Repeat with the remaining two rails (B).
NOTE:
If installing the MSP-YMACC1, insert set screw (L) half
way into the end of rail (A), and then connect to rail (B).
Repeat if using both rails (B).
Figure 2
5.
Place five wall brackets (C) onto rails. (See Figure 3)
NOTE:
Use the sixth wall bracket for MSP-YMACC1.
Figure 3
6.
Add a rail end cap (F) to both ends of each rail.
(See Figure 4)
Figure 4
(H)
(B)
(B)
(B)
(H)
(C)
(F) x 4