background image

C: Above pinion - Nylon angle rack

Foundation

plate

40 - 50

92

147*

Flat bar welded to

foundation plate and rail

* Includes 3mm clearance required 

   between rack and pinion

(Recommended to 

allow for adjustment)

B: Above pinion - Steel rack

Foundation

plate

43 - 53

92

156*

(Recommended to 

allow for adjustment)

Flat bar welded to

foundation plate and rail

* Includes 3mm clearance required 

   between rack and pinion

250mm

Cable conduits

Gate rail

200mm

M10
gearbox
mounting
bolts

400mm

Mount the rack

The rack must be securely 
mounted to the side of the 
gate. It must be parallel 
with the gate rail, and 
there must be a 2 - 3mm 
gap between the teeth of 
the pinion and the rack, 
along the entire travel of 
the gate

Route cables and secure foundation plate

The foundation plate can either be set into a concrete foundation, or 
bolted down onto an existing concrete plinth, refer to illustrations 
below.

Foundation plate installation 

Mounting the 
origin marker

1.

Close the gate completely.

2.

Mount the origin marker to 
the rack a minimum of 
500mm from the origin 
sensor.

1.

Route cables as determined 
in Section 9: Cabling 
requirements. 

2.

The cable conduits or 
SWA cable glands should 
terminate onto the cable 
termination flange provided 
in the foundation plate, as 
depicted in the illustration

3.

Make sure that all cables 
protrude at least 500mm 
from the cable termination 
flange.

3. 

Adjust jacking screws to give 
4-6 mm chassis foundation 
plate clearance.

A 4mm Allen key with 
“ball end” is handy

1.

Insert M8 captive nuts for the 
jacking screws as shown.

2. 

Screw the M8 grub screw 
jacking screws into the 
captive nuts.

Make sure that the M10 
bolts, which secure the 
gearbox, are in place

If bolting the foundation 
plate, the left-hand 
concrete anchor may need 
to be broken off in order to 
clear incoming conduits

3mm

tooth gap

M8 captive nuts

Jacking

Screw

4-6mm

Ensure that all the standard considerations for a quality 
gate installation are adhered to as detailed in 
CENTSYS’ detailed installation manuals.  
These must include:

11. D10/D10 Turbo operator installation

&

Correct access in and out of the premises

&

Endstops are mandatory and must be capable of stopping the 
gate at rated speed

&

Guide-rollers and anti-lift brackets are correctly fitted

&

The gate mass, starting- and rated-pull-force limitations are not 
exceeded

&

The 

D10/D10 Turbo

 is positioned correctly and does not 

protrude into the driveway 

If bolting onto an existing 
concrete plinth, place the 
foundation plate down in the 
correct position and use the plate 
as a template for marking the 
rawl bolt holes.

Ensure that the M10 
gearbox mounting bolts 
are properly tightened

Bolting foundation 
plate onto an existing 
concrete plinth

250mm

200mm

M10

gearbox

mounting

bolts

400mm

Existing 

concrete 

plinth

Option 2: 

Option 1:

 

New concrete foundation

When using a concrete foundation 
it is recommended that the 
foundation plate is welded to the 
rail/track of the gate using a short 
length of flat bar as shown in the 
illustration. This makes it possible 
to complete the whole mechanical 
and electrical installation without 
having to wait for the concrete to 
set. After completing the 
installation the concrete can be 
poured and the operator left in 
manual mode until the concrete 
has set.

• Ensure that the M10  gearbox mounting bolts are properly 

tightened

• Cable conduits must be installed before pouring the concrete

3.

For steel rack mount the 
origin marker onto the rack 
using the bracket provided.

4.

Weld the bracket to the 
rack.

5.

Bolt the origin marker onto 
the bracket using the 
fasteners provided.

Steel rack

6.

With RAZ rack the origin 
marker mounts directly on 
top of the rack without a 
bracket.

7.

Drill mounting holes 
directly into the rack and 
bolt into position.

8.

File away the front lip of 
the rack if you need to 
move the origin marker 
closer to the operator as 
the gate slides past.

RAZ rack

9.

With nylon angle rack it is 
necessary to use the 
bracket provided.

10. It is preferable to use self- 

tapping fasteners to secure 
the bracket into the side of 
the nylon rack as shown.

11. Make a small tack weld to 

secure the back of the 
bracket onto the angle iron 
section of the rack.

12. Bolt the origin marker onto 

the bracket using the 
fasteners provided.

Nylon angle rack

Bolt using
fasteners
provided

Origin marker
bracket

Screw into

 side of the 

nylon rack

Nylon angle rack

RAZ rack

Bolt using
fasteners
provided

Origin marker
bracket

Weld mounting

bracket provided to 

steel rack

Steel rack

Bolt using

fasteners

provided

A: Above pinion - Raz rack

Foundation

plate

40 - 50

92

147*

(Recommended to 

allow for adjustment)

Flat bar welded to

foundation plate and rail

Greater than 500mm

Gate in 

closed

 position

Origin

marker

Origin 
sensor

Plan view

Mounting the origin 
marker (continued)

Apply warning decal/signage

Apply the supplied Warning! decals/signage to the gate 

13. Manually slide the gate 

OPEN until the origin 
marker is in line with the 
origin sensor.

It is possible to make the distance between the marker and the 
sensor much greater than 500mm. However, if using the 
pedestrian opening facility, although the position of the marker 
will not affect the width of the pedestrian opening, it is 
preferable to have the marker mounted inside of the pedestrian 
opening point

14. Ensure distance between 

face of marker and front 
face of sensor is between 
13 and 20mm.

Take care with the 
orientation of the arrow on 
the origin marker. This 
arrow must face the 
operator

15. Adjust distance by sliding 

the origin marker along the 
slotted mounting holes 
until the specified distance 
is achieved.

For best results keep gap 
between marker and 
sensor as small as 
possible

Isometric view

Greater than 500mm

A10

A10

Origin
sensor

Origin

marker

13-20mm

Gate

Rack

Plan view

1.

To ensure operator does not 
protrude into driveway, install 
base plate at least flush with 
the driveway entrance.

2.

Determine a suitable position 
and vertical height for the 
operator by considering 
Figures A, B and C. 

Locate operator position

Steel rack

1.

Fix rack using the steel angle 
brackets provided. 

2.

Brackets must be spaced no 
more than 300mm apart.

3. 

When joining different 
lengths of steel rack, a 
simple way of ensuring 
correct pitch spacing, is to 
clamp a small off-cut 
between the two pieces.

RAZ rack

1.

Use at least three TEK screws per half metre section of rack. 

Fit additional fixing screw through the horizontal slots to secure 
the rack to the gate directly above the pinion when the gate is 
in the closed, pedestrian and open positions

±300mm

±300mm

Gate

closed

Pedestrian

opening

Gate

open

D5

Gate closed

Pedestrian

Gate open

Cable 

termination

flange

M10 
mounting
bolts

500mm

Once the installation has been successfully completed and tested, it is 
important for the installer to explain the operation and safety 
requirements of the system.

NEVER ASSUME THE USER KNOWS HOW TO SAFELY OPERATE 
AN AUTOMATED GATE! 

Even if the user has used one before, it does not mean he knows how 
to SAFELY operate it.  Make sure that the user fully understands the 
following safety requirements before finally handing over the site.

The following needs to be understood by the user:

How to operate the manual release mechanism. 

(Show them how by demonstration)

How the obstruction detection and all other safety features work.  

(Show them how by demonstration)

All the features and benefits of the operator, i.e. safety beams, 
Chronoguard, etc. 

All the safety considerations associated with operating an 
automated gate. The user should be able to pass this 
knowledge on to all other users of the automated system 
and must be made aware of this responsibility.

&

&

&

&

&

Do not activate the gate operator unless 
you can see it and can determine that its 
area of travel is clear of people, pets, or 
other obstructions

&

NO ONE MAY CROSS THE PATH OF A 

MOVING GATE. Always keep people and objects away 
from the gate and its area of travel

&

NEVER LET CHILDREN OPERATE OR PLAY WITH THE 
GATE CONTROLS, and do not allow children or pets near 
the gate area

&

Be careful with moving parts and avoid close proximity 
to areas where fingers or hands could be pinched

&

Secure all easily accessed gate operator controls in 
order to prevent unauthorized use of the gate

&

Keep the automated gate system properly maintained, 
and ensure that all working areas are free of debris and 
other objects that could affect the gate operation and 
safety

&

On a monthly basis, check the obstruction detection 
system and safety devices for correct operation

&

All repair and service work to this product must be done 
by a suitably qualified person

&

This product was designed and built strictly for the use 
indicated in this documentation.  Any other use, not 
expressly indicated here, could compromise the good 
condition/operation of the product and/or be a source 
of danger!

Centurion Systems (Pty) Ltd does not accept any liability caused by 
improper use, of the product, or for use other than that for which the 
automated system was designed.

Ensure that the customer is in possession of the User Guide and 
that you have completed the installation details in the back of 
the User Guide.

CENTSYS operators are designed to be maintenance-free. However, 
there are some basic checks that should be carried out regularly, 
(every six months). These checks will increase the long term reliability 
of the system and prevent erratic operation of your gate. 

Isolate mains supply as well as disconnecting the 
battery before cleaning or working on the equipment.

General

&

Keep the track clear of stones, dirt and obstructions

&

Ensure that all rollers run freely

&

Put the operator into Manual Mode and check that the gate runs 
freely on its rail and does not catch or foul against the walls or 
pillars

&

Ensure that the gate wheels and guide-rollers are rotating freely 
and are not worn. In high-volume applications it will be necessary 
to replace these components regularly

&

Ensure that the rack is properly secured to the gate and that it 
does not press down onto the operator pinion at any point along 
its travel

&

Keep shrubs and vegetation clear of the motor and rack

&

Check that the key still operates the camlock - spray with 
lubrication if necessary

&

Keep the inside of the motor housing clear of insects and dust

Battery

CENTSYS operators, which are fitted with maintenance-free lead acid 
batteries, should provide at least three years of normal service life.

For sites utilising an external large capacity (+/-35Ah) low 
maintenance battery, ensure that the level of liquid (electrolyte level) 
is correct.  

In all instances check for corrosion of the battery terminals. Clean and 
apply copper based grease as necessary.

 

12. Basic maintenance

Charger

The 

D10

 and 

D10 Turbo

 operators have chargers separate to the 

main controller. In the case of product malfunction, the charger fuse 
should be checked, but only by a qualified electrician. Always isolate 
the mains supply to the operator before attempting to remove and 
check the fuse. 

Check the “Mains Present” icon on the main diagnostic screen or 
switch to the battery charger diagnostic screen and check the charger 
voltage – right hand value. This should indicate, 27.6V  for the 

D10 

and 

D10 Turbo.

 Each charger has a red light (LED) to indicate mains 

supply.

Gearbox Oil Level

Check the oil level as described in section 8 of this document or refer 
to the online manuals on our website, 

(www.centsys.com.au). 

Alternatively, please contact your CENTSYS installer for assistance.

13. Installation handover

A10

A10

* Includes 3mm clearance required 

   between rack and pinion

Отзывы: