Technical instructions for the commissioning and adjustment 

 

 

5

4. Installation of Cm Pelet-set 90 
 

Commissioning and fine adjustment of Cm Pelet-set 90 should be carried out by a professional or the 
manufacturer’s authorized fitter. 

 
 
4.1. Installation of pellet burner and pellet control unit on the boiler

 

 

a)  Remove  lower  boiler  door  and  install  lower  boiler  door  CPDV  60/70  for  burner  CPPL-90  (for 

boiler EKO-CK P 70) and CPDV 90/110 (for boilers EKO-CK P 90 and 110) supplied with Cm 
Pelet-set 90 (if lower boiler door CPDV is not already installed on the boiler).  

b)  Disassemble  the  burner  into  4  parts  as  shown  figure  below.  Place  burner  head  (with  fixed 

thicker  gasket  toward  door  and  thinner  gasket  on  the  side  away  from  door)  onto  prepared 
screws on the door, then place a feeding box and tighten the screws with enclosed nuts M8. 
Put a gasket onto the feeding box and put a feeding tube onto it (faced toward the pellet tank, 
either  on  the  left  or  on  the  right  side  and  tighten  it  firmly  using  enclosed  screws  M4  x  30. 
Connect  3-pin  plug  of  the  backfilling  sensor  /  temperature  sensor''  the  supply  pipe  in  3-pin 
connector which is attached to the feeding box. PVC and silicone pipe, which is at its one end 
fixed  to  the  pressure  switch  at  the  burner,  should  be  placed  (and  shorten  if  necessary)  onto 
appropriate  connector  on  the  boiler  door.  Place  cover  onto  preinstalled  screws  and  tighten 
them firmly. In the end it is necessary to put the nozzle of the burner which is attaches to the 
prepared screw on the burner head. 

Содержание Cm Pelet-set 90

Страница 1: ...o Glavna 12 40306 Macinec Croatia tel 385 40 372 600 fax 385 40 372 611 TECHNICAL INSTRUCTIONS FOR THE COMMISSIONING AND ADJUSTMENT Cm Pelet set touch 60 90 kW For boilers EKO CK P 70 110 TUPS 90 T 07 2017 E N eng_1 07 ...

Страница 2: ... set 90 4 1 Installation of pellet burner and pellet control unit on boiler 4 2 Installation of pellet tank CPSP 800 and pellet feeder CPPT 90 5 Start stop 6 Draught of the chimney 7 Automatic pellet refill 8 Initial setting of the regulation 8 1 Setting the configuration 8 2 Setting the protection valve actuator time 3 3 3 5 5 8 9 10 10 10 11 11 12 ...

Страница 3: ...ler control unit CPREG touch 4 pellet feeder CPPT 90 5 pellet tank CPSP 800 3 Technical data Description 1 pellet burner CPPL 90 2 tube for connecting of pellet feeding flexible tube 3 connectors for connecting of burner with control unit 4 Backfilling sensor temperature sensor on inlet tube that is installed tube for connecting of pellet feeding flexible tube backfilling sensor is detailed in the...

Страница 4: ...90 Set thermal output kW 60 70 90 Boiler type EKO CK P 70 EKO CK P 90 EKO CK P 110 Pellet tank volume l 800 Pellet tank height mm 1420 Pellet tank depth mm 980 Pellet tank width mm 1010 Supply voltage V Hz 230 50 Boiler width mm 640 690 690 Lower boiler door CPDV mm CPDV 60 70 for burner CPPL 90 for boiler EKO CK P 70 and CPDV 90 110 for boilers EKO CK P 90 i 110 ...

Страница 5: ...ker gasket toward door and thinner gasket on the side away from door onto prepared screws on the door then place a feeding box and tighten the screws with enclosed nuts M8 Put a gasket onto the feeding box and put a feeding tube onto it faced toward the pellet tank either on the left or on the right side and tighten it firmly using enclosed screws M4 x 30 Connect 3 pin plug of the backfilling sens...

Страница 6: ...Technical instructions for the commissioning and adjustment 6 ...

Страница 7: ...r temperature gauge on inlet tube and other end should be fixed to the feeder so that the tube will not become loosen Transparent tube between the feeder and burner must be as straight as possible so that pellets can fall smoothly from the feeder into the burner if pellets remain in the tube it should be straighten and shorten if necessary g Connect a wire for power supply to the screw feeder CPPT...

Страница 8: ... 90 and 110 with in built Cm Pelet set 90 on heating installation with accumulation tank 1 Boiler EKO CK P 70 90 110 with in built Cm Pelet set 90 2 Accumulation tank CAS 3 Heating pump between boiler and accumulation tank CAS 4 Sanitary water sensor at the lowest sensor sleeve on the accumulation tank 5 3 way thermostat valve for outlet protection as ESBE VTC 512 VTC 531 LTC 141 or Laddomat 21 or...

Страница 9: ...m it pressing the OK button To stop the boiler press ON OFF button and confirm it pressing the OK button 6 Draught of the chimney Chimney of appropriate size is one of conditions for proper operation of the boiler Chimney has to be select according to diagram for solid fuel firing see Technical instructions EKO CK P or EKO CKB P or a chimney with the following minimum draughts has to be select for...

Страница 10: ...wer supply for the filling system LED main switch on when there is power supply Operation mode switch select working mode 0 OFF disabled 1 Auto filling working until tank sensor stops it 2 Manual filling working until manual switching off doesn t working according to tank sensor LED filing on when filling is working manual or auto ...

Страница 11: ...press Installation button SERVICE PIN required 3 In Installation menu press Commissioning button 4 In Commissioning menu press Configuration button 5 In Configuration menu press Configuration button 6 In Configuration menu set scheme 1 scheme CODE 3 characters 2 buttons for changing the values 3 scheme description 7 Set scheme current B 0 0 Confirm it with OK button blue button ...

Страница 12: ...tton 3 In Valve time setting set protection valve actuator opening closing time it depends on the build in protection valve actuator Centrometal d o o shall not be responsible for possible incorrect data caused by printing errors or errors during transcription and in any case it reserves the right to modify its products deemed to be required and useful without any prior notification 1 07 Macinec 0...

Отзывы: