30
Unit start-up
CWP starter has been properly interlocked with the chiller
Oil heaters have been energized for at least 24 hours
Oil level is correct
All discharge, suction and liquid valves are open
Unit has been leak checked (including fittings)
Locate, repair, and report any refrigerant leaks
.................................................................................................................................................................................................................
.................................................................................................................................................................................................................
.................................................................................................................................................................................................................
Check voltage imbalance: AB ................ AC ................. BC..................
Average voltage = ................................... (see installation instructions)
Maximum deviation = ............................ (see installation instructions)
Voltage imbalance = ............................... (see installation instructions)
Voltage imbalance is less than 2%
WARNINg: Do not start chiller if voltage imbalance is greater than 2%. Contact local power company for assistance.
All incoming power voltage is within rated voltage range
Check cooler water loop
Water loop volume = .............................. (litres)
Calculated volume = ............................... (litres)
3.25 litres/nominal kW capacity for air conditioning
6.5 litres/nominal kW capacity for process cooling
Proper loop volume established
Proper loop corrosion inhibitor included .........litres of ...........................
Proper loop freeze protection included (if required) ................ litres of ..............................
Piping includes electric heater tape, if exposed to the outside
Inlet piping to cooler includes a 20 mesh strainer with a mesh size of 1.2 mm
Check pressure drop across the cooler
Entering cooler = .................................... (kPa)
Leaving cooler = ..................................... (kPa)
(Leaving - entering) = ............................ (kPa)
WARNINg: Plot cooler pressure drop on performance data chart (in product data literature) to determine total litres
per second (l/s) and find unit’s minimum flow rate.
Total l/s = .................................................
l/s / nominal kW = ...................................
Total l/s is greater than unit’s minimum flow rate
Total l/s meets job specified requirement of ...................................... (l/s)