The air outlet and return ducts must be calculated in accordance with 

the rated fl ow and the unit’s available pressure(refer to the technical 

characteristics table). The duct calculation and design must be made 

by qualifi ed technical personnel. 

It is advisable to take into consideration the following recommendations:

-  Bends in the fan discharge outlet must be avoided. It is recommendable 

to have a straight section of duct measuring approximately 1 metre. If 

it is not possible, they must be as smooth as possible, using indoor 

defl ectors when the duct is of large dimensions.

-  When making the ducts, direction sharp changes must be avoided 

since they can generate occasional pressure drops, which affect 

the available pressure and the fl ow. The location of discharge 

and aspiration grilles must be studied carefully to avoid the air 

recirculation and the transmission and generation of noises to the 

interior.

-  Flexible connections must be made between the ducts and the unit 

that avoid the noise and vibration transmission.

-  No matter the type of ducts type to use, they must not be composed 

of materials that propagate fi re nor expel toxic gases in the event of a 

fi re. The internal surfaces must be smooth and should not pollute the 

air that circulates within them. In any case, the effective legislation 

about this issue must be respected.  

Caution: 

These units are designed to connect to a duct 

network. If the indoor circuit outlet fan is accessible from 

a particular point in the duct network, the installer must 

fi t a protection mesh in the discharge as per the current 

regulation.

Air ducts connections

-  Before commissioning, check the blade rotation direction and that 

the axis turns without strokes nor vibrations

-  Once running, check the operation conditions: pressures, fl ows and 

consumptions.

-  The coupling of characteristic bends of the fan and the room is 

very important, so that the fl ows and pressures provided to the duct 

network are as required.

Checks at fans

Pulley and belt adjustment 

Both for the indoor circuit motorfans as well as the outdoor circuit are 

coupled by pulleys and belts. In this type of fans, the following must 

be taken into considerations:

-  The pulleys must be on the same plane, so it is important to check 

them with the help of a ruler or a laser aligner.

-  In case they are not aligned, remove the pulley screws, remove the 

pulley and, after removing the hub pin, it can be slided over the axle 

(this action can be performed both in the motor as well as in the fan).

- After fi xing the pulleys on the same plane, the belt tension is made 

by tightening the tensor screw.

-  The belt tension must be checked after 24 hours of motor operation.

Attention:

 Before performing these operations, it is necessary to verify 

that the unit is disconnected from mains.

Pulleys must stay on the same plane

Tensor
screw

Pulley
screws

Taper pin

Condensate drain connection

CONNECT SIPHON

METTRE SIPHON

PONER SIFON

V220014

All models are provided of two condensates drain pans, one in the 

internal circuit and other in the external circuit, 

with independent drainages. Drainage pipe, in 

bronze, gas thread M3/4”.

Installation norms

-  Check that the condensates outlet is not obstructed.

-  All water drain pipes should be provided with a siphon to avoid bad 

odours and water overfl ows.

Содержание 50NF

Страница 1: ...INSTALLATION OPERATION AND MAINTENANCE INSTRUCTIONS 50NZ NF Nominal cooling capacity 17 9 69 6 kW Nominal heating capacity 18 4 73 0 kW 50 Hz Vertical package air conditionners Original document...

Страница 2: ...ns 8 Checks at fans 8 Condensate drain connection 8 9 Safety elements 9 High pressure pressostat 9 Low pressure pressostat 9 Magnetothermals for line protection 9 Automatic switch in the control circu...

Страница 3: ...e of its vertical construction 50NZ Series Air air packaged cooling units 50NF Series Air air packaged reversible heat pumps After their manufacture all units are charged with refrigerant and are test...

Страница 4: ...14 7 13 14 Type Centrifugal Number 1 2 Motor output kW 1 1 1 5 2 2 3 0 1 5 2 2 3 0 Speed r p m 630 680 699 644 680 699 644 Indoor circuit fan Nominal air flow m3 h 4 000 4 600 6 000 7 000 9 200 12 00...

Страница 5: ...location 5 TRANSPORT The unit must be lifted and fixed with care and without inclination maximum inclination 15 since it could harm its operation The unit can be handled with a forklift truck taking a...

Страница 6: ...d and walls in order that the circuit makes the aspiration of the return air 7 LOCATION AND ASSEMBLING Anchorage for antivibrators A B Minimum free space for commissioning and maintenance operations E...

Страница 7: ...th the control in the unit The electrical heaters requested for units already shipped will be sent in a kit and the installer will need to assemble the necessary elements for the operation of the unit...

Страница 8: ...tection mesh in the discharge as per the current regulation Air ducts connections Before commissioning check the blade rotation direction and that the axis turns without strokes nor vibrations Once ru...

Страница 9: ...l circuit Magnetothermal switch that protects the operation circuit against continuous surges as well as against high currents of short duration short circuits Fans and compressors protection Both the...

Страница 10: ...must be emptied Possible water freezing must be avoided glycolling water or by using anti frost thermostat that triggers the circulation pump In models 120 and 160 the hot water coil assembly is carr...

Страница 11: ...e way to avoid breakdowns since the analysis of these data makes early detection of anomalies possible or the provision of the necessary means available to ensure that they do not take place Possible...

Страница 12: ...l and taken from a can tightly closed until the moment of the charge Note Both the oil type as well as the volume needed for each model are stated in the Technical characteristic tables in chapter 3 R...

Страница 13: ...charge fan of the internal circuit Access to the indoor of the frame through this lateral panel Condensates drain pans Access Firstly put the door switch in O position Later unscrew the screws that fi...

Страница 14: ...element are open c Timing of anti cycle short does not allow the starting d Open contact e Contactor coil burnt f Indoor klixon open a Check differential fuses b Verify the safety chain of the electr...

Страница 15: ......

Страница 16: ...Order No 10055 03 2015 Supersedes order No New Manufactured for CARRIER in Spain The manufacturer reserves the right to change the specification without prior notice Printed in the European Union...

Отзывы: