START-UP CHECKLIST
THE RELIABLE OPERATION AND LONG SERVICE LIFE OF THIS EQUIPMENT CAN BE IMPROVED WITH PROPER
INSTALLATION, OPERATION AND REGULAR MAINTENANCE. THE EQUIPMENT IS INITIALLY PROTECTED UNDER
CARRIER’S STANDARD WARRANTY. THIS WARRANTY IS PROVIDED UNDER THE CONDITION THAT THE FOLLOWING
STEPS BE FOLLOWED IN DETAIL. SHOULD ANY QUESTIONS ARISE, PLEASE CONTACT YOUR LOCAL SALES
REPRESENTATIVE OR THE FACTORY BEFORE ATTEMPTING ANY INSTALLATION OR OPERATION OF THE EQUIPMENT.
I. PRELIMINARY INFORMATION
MODEL NO. _______________________________________________ SERIAL NO. ____________________________________
ADDITIONAL ACCESSORIES ________________________________________________________________________________
Receiving and Inspection
WAS THE UNIT RECEIVED UNDAMAGED? (Y/N) __________
IS THERE ANY SHIPPING DAMAGE? (Y/N) __________
IF SO, WHERE: _____________________________________________________________________________________________
___________________________________________________________________________________________________________
WILL THIS DAMAGE PREVENT UNIT START-UP?
(Y/N) __________
WAS THE UNIT RECEIVED COMPLETE AS ORDERED?
(Y/N) __________
ARE “FURNISH ONLY” PARTS ACCOUNTED FOR?
(Y/N) __________
IS THE UNIT ARRANGEMENT/HAND CORRECT?
(Y/N) __________
IS THE UNIT STRUCTURAL SUPPORT COMPLETE AND CORRECT?
(Y/N) __________
Handling and Installation
IS THE UNIT SECURED AND MOUNTED PROPERLY?
(Y/N) __________
ARE MOUNTING GROMMETS/ISOLATORS USED?
(Y/N) __________
IS THE UNIT MOUNTED LEVEL AND SQUARE?
(Y/N) __________
IS PROPER ACCESS PROVIDED FOR THE UNIT AND ACCESSORIES?
(Y/N) __________
IS THE PROPER ELECTRICAL SERVICE PROVIDED?
(Y/N) __________
IS THE PROPER OVERCURRENT PROTECTION PROVIDED?
(Y/N) __________
IS THE PROPER SERVICE SWITCH/DISCONNECT PROVIDED?
(Y/N) __________
IS THE CHILLED WATER LINE PROPERLY SIZED TO THE UNIT?
(Y/N) __________
IS THE HOT WATER LINE PROPERLY SIZED FOR THE UNIT?
(Y/N) __________
IS THE REFRIGERANT LINE PROPERLY SIZED TO UNIT?
(Y/N) __________
ARE ALL SERVICES TO UNIT IN CODE COMPLIANCE?
(Y/N) __________
ARE ALL SHIPPING SCREWS AND BRACES REMOVED?
(Y/N) __________
IS THE UNIT PROTECTED FROM DIRT AND FOREIGN MATTER?
(Y/N) __________
Cooling/Heating Connections
IS FIELD PIPING CONNECTED TO UNIT?
(Y/N) __________
HAS ALL PIPING BEEN PRESSURE TESTED FOR LEAKS?
(Y/N) __________
ARE DRAIN LINE AND TRAPS INSTALLED, AS REQUIRED?
(Y/N) __________
IS ALL PIPING AND VALVES INSULATED, AS REQUIRED?
(Y/N) __________
NOTE: To avoid injury to personnel and damage to equipment or prop
-
erty when completing the procedures listed in this start-up checklist,
use good judgment, follow safe practices, and adhere to the safety
considerations/information as outlined in preceding sections of this
Installation, Start-Up, and Service document.