2.3 - Checks before system start-up

Before the start-up of the refrigeration system, the complete 
installation, including the refrigeration system must be 
verified against the installation drawings, dimensional 
drawings, system piping and instrumentation diagrams and 
the wiring diagrams.

For these checks national regulations must be followed. If 
the national regulation does not specify any details, refer 
to standard EN 378-2 as follows:

External visual installation checks:
• 

Compare the complete installation with the refrigeration 
system and power circuit diagrams.

• 

Check that all components comply with the design 
specifications.

• 

Check that all protection documents and equipment 
provided by the manufacturer (dimensional drawings, 
P&ID, declarations etc.) to comply with the regulations 

are present.

• 

Verify that the environmental safety and protection and 
devices and arrangements provided by the manufacturer 
to comply with the regulations are in place.

• 

Verify that all documents for pressure containers, certifi-
cates, name plates, files, instruction manuals provided 
by the manufacturer to comply with the regulations 

are present.

• 

Verify the free passage of access and safety routes.

• 

Verify the instructions and directives to prevent the 
deliberate removal of refrigerant gases.

• 

Verify the installation of connections.

• 

Verify the supports and fixing elements (materials, 
routing and connection).

• 

Verify the quality of welds and other joints.

• 

Check the protection against mechanical damage.

• 

Check the protection against heat.

• 

Check the protection of moving parts.

• 

Verify the accessibility for maintenance or repair and 

to check the piping.

• 

Verify the status of the valves.

• 

Verify the quality of the thermal insulation and of the 
vapour barriers.

• 

Ensure that the ventilation in the machine room is 
sufficient.

• 

Check the refrigerant detectors.

3 - INSTallaTION SpECIfICS fOR 30RQSY UNITS

3.1 - General

Each fan is controlled by a variable-speed controller. 
Therefore each circuit operates independently and must 
have a separate duct system to avoid any air recycling 
between the air heat exchangers of the different refrigerant 

circuits. 

On the 30RQSY units each fan includes a factory-mounted 
connection frame interface for the connection to the duct 
network of the specific refrigerant circuit to which the fan 
belongs.

 

For the precise dimensions of this connection interface 
please refer to the dimensional drawings for the units.

2 - MOvING aND SITING THE UNIT

2.1 - Moving

See chapter 1.3 - “Installation safety considerations”.

2.2 - Siting the unit

The machine must be installed in a place that is not accessible 
to the public or protected against access by non-authorised 

persons.

In case of extra-high units the machine environment must 
permit easy access for maintenance operations.

Always refer to the chapter “Dimensions and clearances” 

to confirm that there is adequate space for all connections 
and service operations. for the centre of gravity coordinates, 

the position of the unit mounting holes, and the weight 

distribution points, refer to the certified dimensional 

drawing supplied with the unit.

Typical applications of these units do not require earthquake 

resistance. Earthquake resistance has not been verified.

CAuTION: Only use slings at the designated lifting points 

which are marked on the unit.

Before siting the unit check that:

• 

the permitted loading at the site is adequate or that 
appropriate strenghtening measures have been taken.

• 

if the unit has to operate as a heat pump in temperatures 
below 0°C it must be raised at least 300 mm from the 
ground. This is necessary to avoid ice build-up on the 
unit chassis and also to permit correct unit operation in 
locations where the snow level may reach this height. 

• 

the unit is installed level on an even surface (maximum 
tolerance is 5 mm in both axes).

• 

there is adequate space above the unit for air flow and 
to ensure access to the components (see dimensional 
drawings).

• 

the number of support points is adequate and that 

they are in the right places.

• 

the location is not subject to flooding.

• 

for outdoor installations, where heavy snowfall is likely 
and long periods of sub-zero temperatures are normal, 
provision has to be made to prevent snow accumulating 
by raising the unit above the height of drifts normally 
experienced. Baffles may be necessary to deflect strong 
winds. They must not restrict air flow into the unit.

CAuTION: Before lifting the unit, check that all casing 
panels are securely fixed in place. Lift and set down the 

unit  with great care. Tilting and jarring can damage the 
unit and impair unit operation.

If 30RQS/RQSY units are hoisted with rigging, it is advisable 
to protect coils against crushing while a unit is being moved. 
Use struts or a lifting beam to spread the slings above the 
unit. Do not tilt a unit more than 15°.

WArNINg: Never push or lever on any of the enclosure 

panels of the unit. Only the base of the unit frame is 
designed to withstand such stresses.

 

Содержание 30RQ 039 Series

Страница 1: ...s Nominal cooling capacity 40 150 kW Nominal heating capacity 40 160 kW 50 Hz For the operation of the control please refer to the Pro Dialog Control manual for the 30RB 30RQ 017 160 series Installati...

Страница 2: ...with and without hydronic module without filter frame 15 4 6 30RQSY 050 078 option 23B units with and without hydronic module with filter frame 16 4 7 30RQSY 080 120 units with and without hydronic m...

Страница 3: ...stem components 37 15 1 Compressors 37 15 2 Lubricant 37 15 3 Air evaporator condenser 37 15 4 Fans 37 15 5 Electronic expansion valve EXV 37 15 6 Moisture indicator 37 15 7 Filter drier 37 15 8 Water...

Страница 4: ...s to ensure an optimised air flow rate In the cooling mode the full load or part load speed is controlled by a patented algorithm that permanently optimises the condensing temperature to ensure the be...

Страница 5: ...are re installed if the instal lation is changed or for transport with a gas charge All factory installed safety valves are lead sealed to prevent any calibration change The external safety valves mu...

Страница 6: ...to ensure that any leaks are obvious The calibration of a valve that has leaked is generally lower than its original calibration The new calibration may affect the operating range To avoid nuisance tr...

Страница 7: ...ine is under pressure or while it is running Be sure pressure is at 0 kPa and that the unit has been shut down and de energised before removing components or opening a circuit Do not attempt to repair...

Страница 8: ...ease refer to the dimensional drawings for the units 2 Moving and siting the unit 2 1 Moving See chapter 1 3 Installation safety considerations 2 2 Siting the unit The machine must be installed in a p...

Страница 9: ...uare flange is supplied mounted on the unit An available standard round flange can easily be installed at the fan discharge if the installer prefers the use of a round connection duct The unit is supp...

Страница 10: ...he ducts The fan protection grilles can be removed to increase the available pressure At the beginning of each duct provide an access hatch with minimum dimensions of 700 x 700 mm to allow motor repla...

Страница 11: ...installation For the location of fixing points weight distribution and coordinates of the centre of gravity refer to the certified dimensional drawings B In multiple unit installations maximum four u...

Страница 12: ...nd coordinates of the centre of gravity refer to the certified dimensional drawings B In multiple unit installations maximum four units the side clearance between the units should be increased from 10...

Страница 13: ...drawings B Provide a gutter around the unit to collect the condensate water or install the accessory condensate collection pan 30RQSY 039 to 078 C The unit must be installed level less than 2 mm per m...

Страница 14: ...h the unit or available on request when designing an installation For the location of fixing points weight distribution and coordinates of the centre of gravity refer to the certified dimensional draw...

Страница 15: ...e unit or available on request when designing an installation For the location of fixing points weight distribution and coordinates of the centre of gravity refer to the certified dimensional drawings...

Страница 16: ...h the unit or available on request when designing an installation For the location of fixing points weight distribution and coordinates of the centre of gravity refer to the certified dimensional draw...

Страница 17: ...ot obstruct Power cable entry NOTES A Non certified drawings Refer to the certified dimensional drawings supplied with the unit or available on request when designing an installation For the location...

Страница 18: ...ot obstruct Power cable entry NOTES A Non certified drawings Refer to the certified dimensional drawings supplied with the unit or available on request when designing an installation For the location...

Страница 19: ...nlets and outlets 4 11 30RQS RQSY 140 160 units with desuperheater Position of the desuperheater inlets and outlets Unit water inlet and outlet Water inlet and outlet unit with option 49 4 9 30QBS RQS...

Страница 20: ...To find out the unit refrigerant charge please refer to the unit nameplate In accordance with ISO 9614 1 for information only The values have been rounded and are for information only and not contract...

Страница 21: ...To find out the unit refrigerant charge please refer to the unit nameplate In accordance with ISO 9614 1 for information only The values have been rounded and are for information only and not contract...

Страница 22: ...ciency level IE2 3 Year of manufacture This information varies depending on the manufacturer and model at the time of incorporation Please refer to the motor name plates 4 Manufacturer s name and trad...

Страница 23: ...or is specifically designed I Altitudes above sea level m 1000 II Ambient air temperature C 55 IV Maximum air temperature C Please refer to the operating conditions given in this manual or in the spec...

Страница 24: ...of IEC 60364 are accepted as compliance with the requirements of the installation directives Conformance with EN 60204 1 is the best means of ensuring compliance with the Machines Directive 1 5 1 Ann...

Страница 25: ...water or ethylene glycol with various concentrations 30RQS RQSY 039 078 080 160 Static pressure bar 1 2 3 1 2 3 Pure water litres 600 400 200 1680 1120 560 10 ethylene glycol l 450 300 150 1260 840 42...

Страница 26: ...16 165 XLPE Cu 1 x 25 300 PVC Cu 045 1 x 95 1 x 16 165 XLPE Cu 1 x 25 300 PVC Cu 050 1 x 95 1 x 16 165 XLPE Cu 1 x 25 300 PVC Cu 060 1 x 95 1 x 25 210 XLPE Cu 1 x 35 305 PVC Cu 070 1 x 95 1 x 35 220...

Страница 27: ...he materials and coatings to which they are applied This is also the case for the products originally supplied by Carrier 12 WATER CONNECTIONS For size and position of the unit water inlet and outlet...

Страница 28: ...d with nitrogen for a period of one month If the heat transfer fluid does not comply with the Carrier regu lations the nitrogen charge must be added immediately 12 4 Protection against cavitation opti...

Страница 29: ...ation manual 11 Check valve Note x 2 for a dual pump not provided for a single pump 12 Plate heat exchanger 13 Water heat exchanger frost protection heater Installation components 14 Temperature probe...

Страница 30: ...ference of the readings of the pressure gauge connected to the unit inlet and outlet item 19 Let the pump run for two consecutive hours to clean the hydronic circuit of the system presence of solid co...

Страница 31: ...p that corresponds to the nominal flow rate at the required unit operating point NOTE If the system has an excessive pressure drop in relation to the available static pressure provided by the unit pum...

Страница 32: ...advance this can be entered directly as the correct parameter The hydronic circuit cleaning procedure must not be left out 13 4 Units with hydronic module and variable speed pump temperature differenc...

Страница 33: ...low rate l s Water flow rate l s Water flow rate l s Water flow rate l s Legend 1 30RQS 30RQSY 039 2 30RQS 30RQSY 045 3 30RQS 30RQSY 050 4 30RQS 30RQSY 060 5 30RQS 30RQSY 070 6 30RQS 30RQSY 078 Legend...

Страница 34: ...Y 100 4 30RQS 30RQSY 120 5 30RQS 30RQSY 140 Legend 1 30RQS 30RQSY 039 2 30RQS 30RQSY 045 3 30RQS 30RQSY 050 4 30RQS 30RQSY 060 5 30RQS 30RQSY 070 6 30RQS 30RQSY 078 Legend 1 30RQS 30RQSY 080 2 30RQS 3...

Страница 35: ...d 14 3 Operation of two units in master slave mode The control of a master slave assembly is in the entering water and does not require any additional sensors standard configuration It can also be loc...

Страница 36: ...oor air temperature This requires only a 400 V 3 ph 50 Hz power supply source as well as a connection to the unit via a communication bus For the required configuration of the stages consult the 30RB...

Страница 37: ...ndicator Located on the liquid line permits control of the unit charge and indicates moisture in the circuit The presence of bubbles in the sight glass indicates an insufficient charge or non condensa...

Страница 38: ...r condenser is a plate heat exchanger with one or two refrigerant circuits The water connection of the heat exchanger is a Victaulic connection It has a thermal insulation of 19 mm thick polyurethane...

Страница 39: ...ic module option Easy and fast installation reduced power consumption of the water circulation pump 30RQS RQSY 039 160 High pressure variable speed dual pump hydronic module 116K Dual high pressure wa...

Страница 40: ...the whole 30RQS 30RQSY range 18 Partial heat reclaim using desuper heaters option 49 A plate heat exchanger is installed in series with the air condenser coils on the compressor discharge line of eac...

Страница 41: ...er 4 Air condenser coils 5 Expansion valve EXV 6 Damage limitation option in case of a fire safety valve 7 Electric heater to protect the desuperheater against frost not supplied 8 Desuperheater insul...

Страница 42: ...the board refer to the 30RB RQ 017 160 Pro Dialog control manual Other parameters directly affecting the effective capacity reclaimed at the desuperheater are principally The unit load rates that dec...

Страница 43: ...e fittings or the pump every 40 000 hours for applications with water every 15 000 hours for applications with glycol concentrations above 30 To facilitate maintenance operations it is recommended to...

Страница 44: ...pressure jet and a bio degradable cleaner Check the unit operating parameters and compare them with previous values Carry out an oil contamination test Replace the oil if necessary Check and if neces...

Страница 45: ...tal screw Sheet metal plates 4 2 H M6 screw Stauff clamps 10 Earth screw Compressor 2 8 BPHE Brazed plate heat exchanger 20 6 Air heat exchanger We recommend that finned coils are inspected regularly...

Страница 46: ...ressure Saturat temp Relative pressure 20 297 4 807 28 1687 52 3088 19 312 5 835 29 1734 53 3161 18 328 6 864 30 1781 54 3234 17 345 7 894 31 1830 55 3310 16 361 8 924 32 1880 56 3386 15 379 9 956 33...

Страница 47: ...inals are tight All cables and thermistors have been inspected for crossed wires All plug assemblies are tight Check air handling systems All air handlers are operating All chilled water valves are op...

Страница 48: ...an the minimum unit flow rate The flow rate in l s corresponds to the specification of l s Carry out the QUICK TEST function see RB 30RQ 017 160 Pro Dialog control manual Check and register the config...

Страница 49: ......

Страница 50: ...es order No 13465 76 12 2013 Manufacturer Carrier SCS Montluel France Manufacturer reserves the right to change any product specifications without notice Printed in the European Union www eurovent cer...

Отзывы: