Canadian Solar Three Phase Inverter does not require any regular maintenance. However, 

cleaning the dust on heat-sink will help the inverter to dissipate the heat and increase its life 

time. The dust can be removed with a soft brush.

CAUTION: 

Do not touch the inverter's surface when it is operating. Some parts of the 
inverter may be hot and cause burns. Turn off the inverter (refer to Section 
6.2) and wait for a cool-down period before before any maintenance or 
cleaning operation.

The LCD and the LED status indicator lights can be cleaned with a damp cloth if they are too 

dirty to be read. 

NOTE: 

Never use any solvents, abrasives or corrosive materials to clean the inverter.

8. Maintenance

The inverter is designed in accordance with the most important international grid-tied 

standards and safety and electromagnetic compatibility requirements. Before delivering to 

the customer, the inverter has been subjected to several tests to ensure its optimal operation 

and reliability.

In case of failure, the LCD screen will display an alarm message. In this case, the inverter 

may stop feeding into the grid. The failure descriptions and their corresponding alarm 

messages are listed in Table 9.1:

9. Troubleshooting

9. Troubleshooting

Alarm Message

OV-G-V01/02/03/04

OV-G-F01/02

UN-G-F01/02

G-IMP

NO-GRID

OV-DC01/02/03/04

OV-BUS

UN-BUS01/02

GRID-INTF01/02

OV-TEM

Failure description

Over grid voltage

Under grid voltage

Over grid frequency

Under grid frequency

High grid impedance

No grid voltage 

Over DC voltage 

Over DC bus voltage

Under DC bus voltage

Grid interference

Over Temperature 

Solution

1. Resistant of AC cable is too high. 
    Change bigger size grid cable.
2. Adjust the protection limit if it’s 
    allowed by electrical company.

1. Check connections and grid switch.
2. Check the grid voltage inside inverter 
    terminal.

1. Reduce the module number in series.

1. Restart inverter.
2. Change power board.

1. Check PV input connections.
2. Check DC input voltage. 
    (single phase >120V, three phase >350V)
3. Check if PV+/

-

 is reversed.

Inverter no power 
on LCD

No power 

LCD show initializing 
all the time

Can not start-up

1. Check if the connector on main 
    board or

 

power board are fixed.

2. Check if the DSP connector to 
    power board

 

are fixed.

1. Check inverter surrounding ventilation.
2. Check if there’s sunshine direct on 
    inverter in hot weather.

1. Use user define function to adjust the 
    protection limit if it’s allowed by 
    electrical company.

1. Check inverter inductor connection.
2. Check driver connection.

UN-G-V01/02

DC-INTF

DC input overcurrent

1. Restart inverter.

2. Identify and remove the string to the fault MPPT   

.

3. Change power board.

IGFOL-F

Grid current tracking fail

OV-G-I

Over grid current

OV-DCA-I

IGBT-OV-I

Over IGBT current

1.Restart inverter or contact installer.

IG-AD

Grid current sampling fail

1. Remove all DC input, reconnect and
    restart inverter one by one.
2. Identify which string cause the fault and 
    check the isolation of the string.

PV ISO-PRO
01/02

PV isolation protection

INI-FAULT

Initialization system fault

1. Restart inverter or contact installer.

12Power-FAULT

12V power supply fault

DSP-B-FAULT

Comm. failure between main 
and slave DSP

.39.

.38.

Содержание CSI

Страница 1: ...IC 3121 Australia P 61 3 860 918 44 Sales Inquiries Email sales au csisolar com Customer Support Email service au csisolar com South East Asia 101 Thompson Road 15 03 United Square Singapore 307591 P...

Страница 2: ...D 5 Installation 5 1 Select Location for the Inverter 5 2 Mounting the Inverter 5 3 Electrical Connections 7 Operation 6 Start Stop 6 1 Start the Inverter 6 2 Stop the Inverter 1 1 Product Description...

Страница 3: ...V projects This manual covers the three phase inverter model listed below CSI 15K T220GL02 E CSI 20K T220GL02 E CSI 40K T480GL02 E CSI 50K T480GL02 E AC output DC input DC Switch Meter DRM Only for UK...

Страница 4: ...dance with the local and national electrical safety standards WARNING Please don t connect PV array positive or negative to ground it could cause serious damage to the inverter CAUTION The PV array So...

Страница 5: ...cess to modify the adjustable settings the ESC and ENTER keys The two line Liquid Crystal Display LCD is located on the front panel of the Inverter which shows the following information Inverter opera...

Страница 6: ...the equipment to be inspected and in some cases the removal of oxidation and dust that has settled inside the equipment will be required To select a location for the inverter the following criteria s...

Страница 7: ...ble expansion screws to fix the bracket on the wall Figure 5 4 Inverter wall mounting 5 Installation 5 Installation Suitable fixing screws Bracket Back hanging plate size Inverted Figure 5 2 Inverter...

Страница 8: ...connection When connect the AC terminal grounding cable please refer to the contents of 5 3 3 When connect the heat sink grounding cable please follow the steps below 1 Prepare the grounding cable rec...

Страница 9: ...OT cable terminal crimping area 2mm 3mm D C Figure 5 13 Strip wire Important After crimping the terminal to the wire inspect the connection to ensure the terminal is solidly crimped to the wire Ground...

Страница 10: ...ors to the Inverter 5 Measure PV voltage of DC input with multimeter verify DC input cable polar see figure 5 17 and ensure each string of PV voltage in range of inverter operation Connect DC connecto...

Страница 11: ...id terminals are listed as follows Figure 5 23 Strip AC cable NOTE S2 insulation stripping length should be as long as S1 AC terminal cable compression area 10 35 25 3 Leave the AC breaker disconnecte...

Страница 12: ...unication cables through the terminal block as shown in Figure 5 27 Recommended cable cross sectional area is 0 2 1 5mm the cable outer diameter is 5mm 10mm the cable length shall not exceed 3m Figure...

Страница 13: ...zero within 5s Pin5 and Pin6 of RJ45 terminal is used for the logic interface connection Please follow below steps to assemble RJ45 connector 1 Insert the network cable into the communication connecti...

Страница 14: ...Information 6 1 Start the Inverter To start up the Inverter it is important that the following steps are strictly followed 1 Switch the grid supply main Switch AC ON first 2 Switch the DC switch ON If...

Страница 15: ...cks the Screen of LCD I_PV01 05 0A I_PV02 04 9A I_PV08 05 2A V_DC01 Shows input DC voltage I_DC01 Shows input DC current Table 7 1 Information list Status Generating Power 0000W Grid Frequency F_Grid...

Страница 16: ...anced Info and Advanced settings need password Select Advanced Info from the Main Menu The screen will require the password as below YES ENT NO ESC Password 0000 Figure 7 5 Enter password After enter...

Страница 17: ...the energy generation for selected year Press DOWN key to move the cursor to day and year press UP key to change the digit Press Enter after the date is fixed 7 4 7 Daily records The screen shows his...

Страница 18: ...o the previous menu Startup T 10 600S Restore T 10 600S Below is the setting range for User Def Using this function the limits can be changed manually OV G V1 305 332V for 480V 140 152V for 220V OV G...

Страница 19: ...r 7 5 7 Special Settings This function is applicable by maintenance personnel only wrong operation will prevent the inverter from reaching maximum power 7 5 8 STD Mode settings 7 5 9 Restore Settings...

Страница 20: ...t on the DC circuit and shut down the inverter to prevent a fire disaster 7 6 1 Enable the AFCI function The AFCI function can be enabled in the following Path Advanced Setting Password 0010 Special S...

Страница 21: ...nce No grid voltage Over DC voltage Over DC bus voltage Under DC bus voltage Grid interference Over Temperature Solution 1 Resistant of AC cable is too high Change bigger size grid cable 2 Adjust the...

Страница 22: ...y connected wait for the night when the solar irradiance is low and the PV string current down below 0 5A Turn off the two DC switchs and fix the polarity issue Screen OFF with DC applied Inverter int...

Страница 23: ...62727 VDE4105 2018 NB T 32004 IEEE1547 CSI 20K T220GL02 E Safty EMC standard IEC62109 1 2 EN61000 6 2 EN61000 6 3 UL1741 Dimensions W H D Weight 647 629 252mm 45kg 3 PE 480 Max DC input voltage Volts...

Страница 24: ...standard DC connection 1100 4 26 4 40 4 8 0 8leading 0 8lagging 50 60 98 8 98 3 Transformerless 1W 25 60 0 100 Natural convection 4000m Display Communication connections Warranty Rated output power Wa...

Страница 25: ...ompleted Record V AC in Notes 10 Grounding cable Good Poor INSTALLATION Check inverter condition after unpacking Install inverter mounting bracket according to installation instructions in user manual...

Страница 26: ...cable to the communication port 1 Switch the grid supply main Switch AC ON rst 2 Switch the DC switch ON If the voltages of PV arrays are higher than start up voltage the inverter will turn on The re...

Страница 27: ...eted Record address in Notes 7 Machine version For maintenance and reference please record the irmware revisions if applicable Completed Record with serial numbers 8 Operating parameter Record operati...

Страница 28: ...ting tilt Output power Input DC voltage Insulation limit K PV start up voltage Grid V Max V Min Frequency Max Min Reactive compensation PF Coniguration MPPT Individual MPPT Parallel Monitoring RS485 E...

Страница 29: ...to inverter site selection and installation 3 PHASE STRING INVERTERS KTL SERIES CSIF ST 016 A 0 INSTALLER S NAME INSTALLER S SIGNATURE COMPANY DATE Inverter serial numbers 1 2 3 4 5 6 7 8 9 10 11 12 1...

Отзывы: