7. Normal operation

7. Normal operation

7.5.11.2 Backflow Power

->Set Backflow Power 

Figure 7.

 Set the 

 p

o

wer 

25

backflow

Figure 7.26

Press the UP/DOWN keys to set data.Press the ENTER key to set backflow power.  

Then press DOWN keys to move the cursor, press UP to change the number.  

Press the ESC key to save the settings and return to the previous menu.

The setting is used to define the allowed export power into the grid.

The setting range is between 00000W to 29900W.

YES=<ENT>  NO=<ESC>

Power:-00000W

7.5.11.3 Fail safe ON/OFF

This setting is used to give out an alarm (stop inverter generation as well) when the Meter 

connection is lost during operation.

It can prevent potential backflow power into the grid when the system loses control.

Figure 7.27 Set the

 

Fail

 

Safe ON/OFF

YES=<ENT>  NO=<ESC>

Fail

 

Safe Set:ON

It is only mandatory to turn on this function when the inverter is installed in UK due to the G100 

regulation. For other regions,customers can enable or disable the function as they desire.

NOTE: 

When the failsafe function is ON and CT/Meter is disconnected somehow, 
the inverter will stop generation and give "Failsafe" alarm on the LCD.
When the failsafe function is OFF and CT/Meter is disconnected somehow, 
the inverter will keep the output power as the last moment when the 
CT/Meter is still connected. After a restart, the inverter will output at full 
power without limit.

Select EPM Settings from the Main Menu to access the following options: 

1. Mode Select    2.

Backflow Power    3.

Fail safe ON/OFF    4.

Backflow Work Mode    

7.5.11.1 Mode Select

There are 4 settings in this menu as below:

1. OFF    2. Meter in Load    3. Meter in Grid   4.Consumption Monitor

OFF: 

Functions are disabled

Meter in Load: 

Canadian Solar Smart Meter is connected in the load branch circuit.

Meter in Grid: 

Canadian Solar Smart Meter is connected in the grid connection point 

(The backflow power is default as 0W).

Consumption Monitor: 

Canadian Solar Smart Meter is connected in the grid connection 

point (The backflow power setting is not applicable).

Please refer to below instructions for different user scenarios.

Scenario 1. Only Function 1 is required

Step 1: Refer to Section 4.3 to connect the smart meter on the grid side or load side.

Step 2: Select the Section 7.5.11.1 Mode Select as Option 2(Meter in Load) or 

             Option 3 (Meter in Grid) accordingly.

Step 3: Configure the Section 7.5.11.2 to set the allowed backflow power.

Step 4: Configure the Section 7.5.11.3 to enable the failsafe function (If necessary).

Step 5: Configure the Section 7.5.11.4 to modify the work mode (If necessary).

Scenario 2. Both Function 1 and 2 are required

Using a Smart Meter:

Step 1: Refer to Section 4.3 to connect the smart meter on the grid side.

Step 2: Select the Section 7.5.11.1 Mode Select as Option 3(Meter in Grid).

Step 3: Select the Section 7.5.2.2 24H Switch as "Enable".

Step 4: Configure the Section 7.5.11.2 to set the allowed backflow power.

Step 5: Configure the Section 7.5.11.3 to enable the failsafe function (If necessary).

Step 6: Configure the Canadian Solar monitoring system 

             (Please refer to the manual of monitoring device).

If customer does not want to enable the export power control function, please change 

the "backflow power" to the max output power of the inverter in Step 4 OR simply 

select the mode as "consumption monitor" in Step 2 and skip Step 4-5.

Содержание CSI-25K-T220GL03-E

Страница 1: ...ail sales au csisolar com Customer Support Email service au csisolar com South East Asia 101 Thompson Road 15 03 United Square Singapore 307591 P 65 6572 905 F 65 6559 4690 Sales Inquires Email sales...

Страница 2: ...Shutdown 6 1 Start up procedure 6 2 Shutdown procedure 39 39 39 7 1 Main Menu 40 42 7 2 1 Lock screen 40 7 2 Information 4 1 Inverter monitoring connection 28 7 Normal operation 40 4 2 DRM Connection...

Страница 3: ...n Solar distributor Cross screws M4 14 x4 Cross Recessed Hexagon Bolt M6 12 x2 User manual x1 Manual AC terminal cover x1 DC connectors 25 30 K x8 50K x10 60K x12 4pin COM Port 16pin COM Port 16pin CO...

Страница 4: ...tallations must be done in accordance with local and national electrical safety standards 1 3 Storage 2 Safety Instructions WARNING To reduce the risk of fire branch circuit over current protective de...

Страница 5: ...ff before the DC Switch is turned off 2 3 Notice for use 2 Safety Instructions 3 1 Environmental considerations 3 1 1 Select a location for the inverter When selecting a location for the inverter cons...

Страница 6: ...electricity supply the sound level from the inverter can be quite high 3 2 Product handling Figure 3 3 Handles used to move the inverter shown circled in red 3 1 2 4 Air circulation Do not install in...

Страница 7: ...ally The steps to mount the inverter are listed below 1 Refer to Figure 3 6 drill holes for expansion bolt M10 90 based on the hole diameter of bracket using a precision drill keeping the drill perpen...

Страница 8: ...from vertical The steps to mounted to the rack are listed below 3 Install mounting plate 1 Remove the bracket and fasteners from the packaging Mark the position for hole drilling according to the hol...

Страница 9: ...he Grid Supply Main Switch AC OFF 2 Switch the DC Isolator OFF 3 Connect the inverter to the grid 4 Assemble PV connector and connect to the Inverter Inverter design uses PV style quick connect termin...

Страница 10: ...nding 2 Prepare OT terminals M10 To effectively protect the inverter two grounding methods must be performed Connect the AC grounding cable Please refer to section 3 4 3 Connect the external grounding...

Страница 11: ...This can cause serious damage to the inverter WARNING MAKE SURE the polarity of the PV array output conductors matches the DC and DC terminal labels before connecting these conductors to the terminal...

Страница 12: ...d between the inverter and the grid Table 3 2 Rating of grid OCPD 3 4 3 1 Connecting the inverter to the utility grid All electrical installations must be carried out in accordance with the local stan...

Страница 13: ...n use a hydraulic crimp tool to crimp the terminal The crimped portion of the terminal must be insulated with heat shrinkable tube or insulating tape 1 Strip the end of AC cable insulating jacket abou...

Страница 14: ...12 5 13 6 14 7 15 8 16 Meter RS485 B DRM 2 6 COM1 485 A DRM 3 7 COM1 485 B DRM 4 8 RefGen COM2 485 A Com DRM0 COM2 485 B V 12V V GND Figure 4 1 16pin COM Connector The following is the assembly diagra...

Страница 15: ...box or any compatible 3rd party monitoring devices PPC or plant SCADA 4 Comm Monitoring 4 Comm Monitoring 29 28 4 1 Inverter monitoring connection Canadian Solar can provide optional accessories such...

Страница 16: ...Comm Monitoring 4 Comm Monitoring 31 30 NOTE The PLC communication can not work with RS485 communication at the same time If already installed the PLC CCO for PLC communication on site then the RS485...

Страница 17: ...n Connector 4 3 Meter Connection The inverter can work with a three phase smart meter to achieve Export Power Management function and or 24hour consumption monitoring function The Pin 1 and Pin 2 of t...

Страница 18: ...service technicians only The inverter is customized according to the local grid standard before shipping There should be no requirement to set the standard NOTE The User Def function can only be used...

Страница 19: ...the inverter see Specifications in section 10 may damage the inverter Although Canadian Solar inverters feature reverse polarity protection prolonged connection in reverse polarity may damage these p...

Страница 20: ...ed DC POWER LED and LCD will be continuously lit 4 Canadian Solar inverters are powered from the DC side When the inverter detects DC power that is within start up and operating ranges the inverter wi...

Страница 21: ...1 Information list Status Generating Power 0000W Grid Frequency F_Grid 00 00Hz Total Energy 0000000 kwh This Month 0000kwh Last Month 0000kwh Today 00 0kwh Yesterday 00 0kwh 10 sec 10 sec 10 sec 10 s...

Страница 22: ...arm Message 2 Running message 3 Version 4 Daily Energy 5 Monthly Energy 6 Yearly Energy 7 Daily Records 8 Communication Data 9 Warning Message The following submenus are displayed when the Settings me...

Страница 23: ...history of changing settings Only for maintance personel 7 Normal operation 7 Normal operation 7 4 3 Version The screen shows the model version of the inverter And the screen will show the software v...

Страница 24: ...99 Figure 7 16 Selecting the User Def menu will access to the following submenu see Figure 7 17 Figure 7 17 OV G V1 400V OV G V1 T 1 0S Below is the setting range for User Def Using this function the...

Страница 25: ...alue of total energy Use this function could allow user to revise the value of total energy to the same value as before If the monitoring website is used the data will be synchronous with this setting...

Страница 26: ...not connected or logic interface relay is opened the inverter will display LimbyDRM and the inverter output power will be limited to zero 1 Select Initial Settings 2 Select DRM and set it to ON 7 5 10...

Страница 27: ...ere are 4 settings in this menu as below 1 OFF 2 Meter in Load 3 Meter in Grid 4 Consumption Monitor OFF Functions are disabled Meter in Load Canadian Solar Smart Meter is connected in the load branch...

Страница 28: ...als to one of three phase load power that is the lowest load power of a certain phase Figure 7 31 Inverter Meter 7 5 13 Restart HMI The function is used for restart the HMI This function is applicable...

Страница 29: ...Test Figure 7 33 Selecting Fan Test displays the sub menu shown below Are you sure YES ENT NO ESC Fan Test is a factory test function Press the ENTER key to start the test Press the ESC key to return...

Страница 30: ...t When operating the inverter LCD screen displays PID repairing information and the red light is on The Night Time PID Recovery function is always ON when AC is applied If maintenance is required and...

Страница 31: ...xed 2 Check if the DSP connector to power board are fixed 1 Check inverter surrounding ventilation 2 Check if there s sunshine direct on inverter in hot weather 1 Use user define function to adjust th...

Страница 32: ...ing current down below 0 5A Turn off the two DC switchs and fix the polarity issue Screen OFF with DC applied Inverter internally damaged 1 Do not turn off the DC switches as it will damage the invert...

Страница 33: ...CSI 50K T400GL03 E Max output current Amps 83 6 3 N PE 220 380 230 400 Rated grid output current Amps 10 Specifications AC connection DC connection Display Communication connections MC4 connector OT...

Страница 34: ...0 195 CSI 25K T220GL03 E Max output current Amps 72 2 3 N PE 220 Rated grid output current Amps AC connection DC connection Display Communication connections MC4 connector OT Terminal max 70 mm LCD Ca...

Страница 35: ...ances and are properly ventilated Completed 5 Serial number Record the product serial numbers located on the side label Serial Numbers attached list 6 Solar modules Confirm PV module installation comp...

Страница 36: ...0GL01 E CSI 8K T400GL01 E CSI 10K T400GL01 E 1 Switch the grid supply main Switch AC ON first 2 Switch the DC switch ON If the voltages of PV arrays are higher than start up voltage the inverter will...

Страница 37: ...e front panel interface Completed Record current date time in Notes 6 Communication setting if avail Set communication with a unique address for each inverter Completed Record address in Notes 7 Machi...

Страница 38: ...Output power Input DC voltage Insulation limit K PV start up voltage Grid V Max V Min Frequency Max Min Reactive compensation PF Configuration MPPT Individual MPPT Parallel Monitoring RS485 Ethernet...

Страница 39: ...r to inverter site selection and installation 3 PHASE STRING INVERTERS CSIF ST 016 A 0 INSTALLER S NAME INSTALLER S SIGNATURE COMPANY DATE Inverter serial numbers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1...

Отзывы: