Place the plate over the iron cage.
Fill the foundation frame with concrete; the base must be perfectly level and the screws' threading completely above surface.
Wait at least 24 hrs for the concrete to solidify.
Remove the foundation frame.
Laying the anchoring plate
Set up a foundation frame that is larger than the anchoring plate and sink it into the dug hole.
Fit an iron cage into the foundation frame to reinforce the concrete.
Assemble the four anchoring braces to the anchoring plate.
INSTALLING
⚠
The following illustrations are mere examples. Consider that the space available where to fit the barrier and accessories will vary depending on
the area where it is installed. It is up to the installer to find the most suitable solution.
⚠
Caution! Warning! Use hoisting equipment to transport and position the barrier.
During the set up and installing stages the barrier could be unstable and tip over. So, be careful and do not lean on it until it is fully fastened.
Preliminary operations
⚠
If the flooring does not allow for a sturdy fastening of the entry unit, you will have to set up a cement slab.
Dig a hole for the foundation frame.
Set up the corrugated tubes needed for the wiring coming out of the junction pit.
The number of tubes depends on the type of system and the accessories you are going to be fit.