5 Commissioning
5.1
Commissioning procedure
To start the commissioning procedure, follow the steps bellow:
1. Connect a Manometer to the gas inlet pressure test nipple on the burner gas inlet
connection.
2. Locate CO/CO
2
combustion analyser into flue pipe as close as possible to the appliance
outlet.
3. Confirm and record that adequate ventilation is available for the safe operation of the
burners.
4. Establish that the system pipe work is complete, full, purged and adequate system load and
circulation exists to facilitate firing of the burners.
5.
Turn ‘On’ the gas supply and ensure adequate static gas pressure is available at the burner
inlet.
6. Locate the position the position of the Throttle adjustment screw (High rate throttle adjuster)
7.
Locate the position of the Offset adjustment screw (Low rate offset adjuster).
1 Throttle Adjustment Screw
2 Offset Adjustment Screw
3 Reset Button
4 Indicator Light (Alarm)
Содержание Inverterjet 50M
Страница 4: ...Installation Service User Manual BURNERTECH 3...
Страница 18: ...Installation Service User Manual BURNERTECH 17 Flow chart fan speed...
Страница 19: ...Installation Service User Manual BURNERTECH 18 6 User Instructions 6 1 Limitations on use of Burner...
Страница 26: ...Installation Service User Manual BURNERTECH 25 7 3 4 Maintenance Notes...
Страница 27: ...Installation Service User Manual BURNERTECH 26...
Страница 28: ......